Northwise

Nebius Indiana: DataOne's Frankfort Data Center

Research Note · FreePublished

A trip to Vineland and a familiar power supplier make Nebius a plausible tenant in Frankfort.

In this article

When officials in central Indiana wanted to see what DataOne might build in their community, the developer’s reference site was in southern New Jersey. In November 2025, local officials arranged a visit to Vineland, New Jersey, where DataOne was building a data center to Nebius’s design. They wanted to ask their counterparts what happened to power rates, how much water the facility used and what people living nearby could hear. Account of the delegation and its purpose · Nebius on its Vineland design

A year later, DataOne has a zoning vote for a 600,000-square-foot AI data center in Frankfort, Indiana. The developer proposes 350 MW from the grid and 175 MW from fuel cells on site. It identifies Bloom Energy, the supplier already powering Nebius equipment at Vineland. Frankfort zoning hearing · DataOne’s project answers

Nebius is a credible candidate to take space here. Its engineers already know how to deploy their equipment in a DataOne building, and its CEO wants to use Bloom at more sites. That makes Frankfort worth following for the next round of US expansion. The public trail reaches the developer and the power supplier. The name on the Indiana lease is still missing.

What the city heard about the tenant

In February, Mayor Judy Sheets laid down a condition for restarting discussions. She wanted the city dealing directly with DataOne, which she called the “end user representative of the facility.” It is an important choice of words. The mayor identified who could speak for the project. She did not identify the company that would run the computers. Mayor’s February 2 statement

DataOne itself distinguishes the tenant from the customer. It says it expects to announce their identities with them after approvals. Its staffing plan makes the distinction more tangible. Of roughly 200 operating jobs, it expects about 100 to work for DataOne and another 100 to work on the tenant’s behalf. DataOne on disclosure and hiring

Vineland shows how that arrangement can work. DataOne supplies the facility, Nebius supplies the GPU infrastructure and Microsoft buys access to the compute. Nebius’s September 2025 SEC filing identifies Vineland by name. It also allows for alternative capacity in the event of a missed delivery. No Indiana location appears in that provision. Microsoft agreement, Form 6-K

The New Jersey visit also had a practical consequence back home. Frankfort councilman Steve Beardsley said the city wrote specific noise protections into its agreement after learning about complaints in Vineland. That is a direct link between the projects, down to the conditions the city wanted before welcoming the same builder. Beardsley’s September remarks

The clue in the earnings call

On November 12, an analyst asked Nebius why its Microsoft deliveries in New Jersey had slipped. Infrastructure chief Andrey Korolenko said DataOne had wound down temporary generation sooner than expected while the Bloom installation was ramping. The fuel cells were already supplying power. Then CEO Arkady Volozh volunteered something about what came next. He said, “we plan to use more Bloom generation on our other sites.” Q3 earnings call, Vineland Q&A

That remark followed a long-term US power partnership Nebius and Bloom signed in May. In September, electrical engineer Kevin Thomas told Frankfort residents exactly where Bloom would fit in DataOne’s design. Its fuel cells would provide the 175 MW generated on site. Nebius and Bloom announcement · Thomas at the Frankfort open house

Then DataOne CEO Charles-Antoine Beyney connected the two projects himself. In an October 27 interview, he said Indiana construction would run on the grid and ruled out the temporary gas generators that had drawn objections at Vineland. The fuel cells were part of the plan for the finished Indiana facility. Beyney’s interview on WILO

Put the two executives’ accounts together and there is a reason for Nebius to work with this developer again. Frankfort was designed around a power source its engineers had learned to bring online in New Jersey, with a different plan for construction power. Another tenant could buy the same design. Bloom also has a large supply agreement with Oracle. Bloom’s Oracle agreement

Nebius’s earnings maps offer a separate test. On page two of both its Q2 and Q3 shareholder letters, the two close markers in the central US are labeled Kansas City and Missouri. The next pair to the east is Pennsylvania and New Jersey. Neither map labels Frankfort or Indiana. The company’s November call also put no Indiana location behind Volozh’s comment. Q2 shareholder letter · Q3 map, page 2

North American portion of Nebius’s Q3 map showing the labeled US and Canadian sites and the company’s pin legend.
Nebius’s November 12 shareholder letter, page 2. The map distinguishes existing sites from 2026 additions. Its labeled Midwest locations include Minnesota, Kansas City and Missouri.

The independent tracker does pin Frankfort, but its own Indiana entry calls the tenant write-up “Informed Speculation.” The investor discussion points back to the same two suppliers. Counting those mentions as additional confirmations would count the same clue twice. Independent tracker entry · Original investor discussion

The field that became a one-building proposal

The land is in Washington Township, west of downtown Frankfort, on the Logix Innovation Campus near the municipal airport. The zoning notice names DataOne Frankfort LLC and traces 115.391 acres along the Norfolk Southern railroad in the Park 300 West industrial area. The site was zoned for industry while the land was still leased for farming. City project announcement · Parcel description, case 2026-026

Parcel boundary reconstructed from the bearings and distances in the hearing notice.
The survey bearings trace the land in the application. The equipment layout is a separate development-plan decision.

The design has changed twice on paper. The April 2025 plan contemplated seven buildings totaling about a million square feet. DataOne’s project FAQ later described about 800,000 square feet and a $7.5 billion investment. On November 10, 2026, the zoning board considered a single building of about 600,000 square feet. April zoning minutes · November hearing account

The board voted 4–0 for the special exception and two variances, covering building height and the surface of 60 parking spaces. The sound wall still needs its own hearing. Before filing the development plan, DataOne must bring back the wall proposal and a noise study.

Beyney also identified drainage approval as a step before the building permit. The agreement requires noise, environmental and traffic studies before groundbreaking. For a neighbor, those are the documents that will show where the cooling equipment goes, what can be heard beyond the fence and how traffic reaches the site. Beyney on the outstanding permits and studies

Who would supply 525 MW

The earliest public power figure was up to 300 MW. In May 2025 the municipal Utility Service Board approved a conditional, nonbinding willingness-to-serve letter for the prospective project. Utility officials described the line and substation work it would require. Utility board’s May vote and conditions

DataOne now proposes 350 MW from the grid, 50 MW above that earlier letter, plus 175 MW generated on site by gas-fed fuel cells. Frankfort Municipal Utilities would take wholesale power from the Indiana Municipal Power Agency. DataOne says it will fund two substations, keeping one for the campus and transferring the other to the municipal utility. DataOne’s power plan

Two proportional bars show 350 MW proposed grid supply and 175 MW proposed on-site fuel cells.
The 525 MW is DataOne’s proposed site supply. The earlier utility letter covered up to 300 MW. No public allocation assigns any of this power to Nebius.

A signed service agreement for 350 MW, with an energization date, would settle the next power question. The tenant’s usable IT load is a different number. Cooling, power conversion and the rest of the building also draw electricity. DataOne plans closed-loop cooling and dry coolers, which is one reason the city wants to see the sound study.

The first money has reached Frankfort

On September 28, the Common Council voted 5–2 for the community enhancement agreement. Mayor Sheets later confirmed that DataOne’s first $1 million had reached the city’s general fund. She said the next $1 million was due at permitting. Frankfort has already collected real money while the developer still has studies and hearings ahead. September council minutes · Mayor’s November interview

Ordinance 26-35 went on the November 23 council agenda for a second reading. It concerns a conditional agreement to help finance the project from the incremental property taxes the development would generate. The city has posted the meeting recording. As of the morning of November 24, its document center carried the agenda but no adopted minutes for that meeting. Council agenda · City recording · Published financing notice

The Redevelopment Commission scheduled its own public hearing and two DataOne resolutions for 5:30 p.m. on November 24. Its attorney explained that placing the parcel in a new tax district lets the city capture future growth in assessed value. The zoning board still has to hear the sound proposal before DataOne can apply for its development plan. Commission agenda · Commission attorney’s explanation

Frankfort Redevelopment Commission agenda listing the public hearing and two DataOne resolutions for November 24.
The commission’s agenda puts both financing resolutions after the public hearing.
Frankfort’s community agreement, zoning decision, scheduled financing votes and remaining sound review.
The September agreement brought money into the city. The November zoning decision left the sound study and wall hearing ahead of the development plan.

Where Indiana fits on the Nebius calendar

DataOne allowed 18 to 24 months for construction after a possible start in late 2026 or early 2027. On those assumptions, the full build points roughly to mid-2028 through early 2029. An earlier first hall is possible, but DataOne has given no phased handover date. Its public schedule gives us no basis to add Indiana megawatts to the 2027 Nebius ramp. Developer’s construction timetable

What Nebius could gain here is another large US location where a partner finances the site infrastructure and handles the local power build. That can sit alongside owned campuses such as Independence, especially if customers want compute before Nebius can finish its next owned building. Vineland also shows the price of that arrangement. When a landlord changes the power schedule, Nebius still has a delivery date to meet. Nebius’s filed Q3 capacity update · Northwise Nebius site hub

An Indiana equipment filing or a site-specific Nebius operations job could put the company on this parcel before a press release does. The clearest answer would come from DataOne itself. It has told residents it will announce the project with the tenant and customer once approvals are in hand. Until then, the place to measure how this partnership performs for Nebius is the campus already delivering to Microsoft. Northwise Vineland site report