NBIS Stock Vineland NJ Data Center
Nebius Vineland explained: campus capacity, development phases, Bloom fuel cells, Microsoft contract, permits and the outlook, with tracker and model links.
In this article
DataOne was supposed to keep its temporary generators running until Bloom Energy’s fuel cells could take over at Vineland. New Jersey regulators found that DataOne had been running the gas engines without the required air permits. In late Q3, DataOne began winding down its temporary generation faster than Nebius had planned. Bloom couldn’t replace that power fast enough. Nebius says the gap delayed Microsoft deliveries that had been slated for 2026. Nebius November earnings call · NJDEP enforcement announcement
The old schedule put the Microsoft rollout through the end of 2026. On November 12, Nebius said it expects to deliver more than half of the contracted capacity by year-end. The rest is now scheduled for Q2 2027. Nebius annual filing · November SEC filing
Vineland is already in service for Microsoft. Nebius delivered the first GPU tranche in November 2025 and reported further handovers into November 2026. Bloom is now supplying power as more fuel-cell blocks go in. Nebius annual filing · November SEC filing

The site and the companies behind it
The data center sits at 3963 South Lincoln Avenue in South Vineland, on a former sand-mining property. The land was once earmarked for the Silica Sands golf course. By March 2025, Nebius and DataOne were pitching a purpose-built AI campus expandable to 300 MW. The South Jersey location gave Nebius room to build and a foothold near Philadelphia and the Northeast’s customers. City planning notice · Land-use history · Nebius’s March 2025 announcement

DataOne owns and operates the facility. Northeast Precast is the local construction partner. Nebius installs and runs the servers and networking, and Microsoft buys dedicated GPU capacity from Nebius. Bloom builds, operates and maintains the fuel-cell systems under a separate power agreement. Nebius project page · Fuel-cell agreement filing

Current active capacity and planned campus size
Nebius delivered the first Microsoft tranche in November 2025 and the second in February 2026. It reported two deliveries in the month leading up to its August update and further handovers through Q3 and into November. Nebius hasn’t disclosed how many IT megawatts are live or how much capacity each handover added. Nebius annual filing · August shareholder letter · November SEC filing
In August 2025, Nebius put contracted New Jersey power under construction at 200 MW, with 100 MW due in 2025 and another 100 MW in 2026. DataOne later described a 14-hall campus with a maximum of 350 MW. Nebius’s original description was up to 300 MW. The figures come from different announcements, and the companies haven’t reconciled them. August 2025 shareholder letter · DataOne project FAQ · Nebius’s March 2025 announcement
The Bloom contract illustrates the difference between what can be installed and what can be delivered. The agreement calls for about 328 MW of installed fuel cells and about 250 MW of guaranteed power across three phases. Cooling and building systems draw from the site’s power supply alongside the servers. Fuel-cell agreement filing
Figure | Scope | Source |
|---|---|---|
200 MW | Contracted power under construction in the 2025 plan. The schedule called for 100 MW in 2025 and 100 MW in 2026. | |
Up to 300 MW | Original Nebius campus expansion plan. | |
Up to 350 MW | DataOne’s later maximum for its 14-hall buildout. | |
328 MW installed / 250 MW guaranteed | Expected fuel-cell system and contractual supply across three phases. |
What is actually being built
At its August 17 meeting, the Vineland Planning Board approved a revised two-phase plan. The buildings are a 129,622-square-foot data center and a 587,980-square-foot, two-story expansion attached to it. The notice listed both as under construction at the time. Together they account for just over 717,000 square feet of data-center space in a much larger development. City planning notice · August 17 meeting minutes
Much of the rest of the site is devoted to keeping those halls powered and cooled. The approved plan includes four ground-mounted Bloom fields and five multistory power structures, a 92,466-square-foot chiller building, LNG storage and filling equipment, a 6,750-square-foot water-treatment plant and 161,896 square feet of Megabay structures. City planning notice

Why the power strategy is central to the project
Vineland was designed to make most of its electricity on site, so DataOne could build its power supply alongside the halls. Nebius signed its agreement with Bloom in May 2026 to replace the planned reciprocating engines with solid oxide fuel cells. Both systems use natural gas. The fuel cells use an electrochemical reaction to generate electricity, and the approved design includes on-site LNG storage. Nebius and Bloom announcement · City planning notice

Nebius infrastructure chief Andrey Korolenko said DataOne’s engines were meant to cover the period when only part of the Bloom system would be ready. By winding down early, DataOne took away power Nebius had counted on for new Microsoft capacity. Bloom reported that its first block was ready on October 22. By the November call it was supplying the site and Nebius was accelerating the installation of the remaining blocks. Bloom earnings call · Nebius November earnings call
DataOne’s FAQ lists a 5 MW municipal supply and describes a proposed 49 MW feed from Atlantic City Electric. The design assigns the grid a backup role for critical network equipment, with Bloom supplying the halls and mechanical systems. DataOne project FAQ
Power economics and the cost of getting the timing wrong
The Bloom agreement buys power as a service. Bloom installs, operates and maintains the equipment, while Nebius pays for capacity and electricity. The filing describes three expected phases with a ten-year supply term for each and up to $2.6 billion in service fees over the life of the agreement. Fuel-cell agreement filing
Bloom separately described a $1.7 billion project investment with financing and development support from Industrial Development Funding, Oaktree, Morgan Stanley and MUFG. That financing supports the power assets. Nebius is paying to run compute against the supply, while Microsoft’s payments depend on the delivery and availability of the GPU service. A delay pushes back the point when a new cluster can contribute revenue. Bloom project financing · Nebius annual filing
The computing and cooling inside the campus
The GPUs run in clusters, with networking, storage and cooling commissioned before Nebius can hand them over to Microsoft. Vineland’s cooling design calls for a one-million-gallon initial fill, then recirculates water in a closed loop. The chillers are housed indoors to reduce noise, and the site plan includes a water-treatment plant. At the August hearing, residents and experts raised questions about drainage and groundwater on the former mining property. Nebius project page · August 17 meeting minutes
What Microsoft brings to Vineland
Microsoft signed for five years of dedicated GPU capacity at Vineland, delivered in tranches. Nebius put the base agreement at about $17.4 billion through 2031, with additional capacity and services potentially taking it to about $19.4 billion. The annual filing estimates about $6.96 billion in aggregate upfront payments and monthly billing for the rest over the service terms of each tranche. Microsoft agreement SEC filing · Nebius annual filing

The contract gave Nebius a customer to build around and a way to fund some of the GPU deployment. When Nebius announced the deal, it planned to use Microsoft cash flows and borrowing secured against the agreement. Microsoft can receive service credits or terminate individual tranches under specified delivery or availability conditions. Contract announcement · Nebius annual filing
Nebius’s August letter said it had “delivered all capacity tranches to Microsoft” and mentioned two deliveries in the preceding month. The November filing shows the rollout continued beyond that update, with new handovers and more capacity still due. August shareholder letter · November SEC filing
Local approvals, temporary generators and community concerns
In September, NJDEP assessed a $1.072 million penalty over 62 natural-gas engines installed and operated without preconstruction permits or operating certificates. The engines were rated at 1,982 kW apiece, roughly 123 MW of installed generation across the fleet. The agency cited the equipment DataOne had used to supply the site during the transition. NJDEP enforcement announcement
DataOne asked for an administrative hearing and a stay on October 9, challenging the state’s permit determination and penalty. The original 45-day period ran to November 6. State senator Michael Testa asked NJDEP for an update on November 9. Whether the stay was granted or the remaining engines were permitted is still open in the public record. Clean Air Act notice, pp. 8–9 · Testa’s letter to NJDEP
The August planning vote approved the revised building and power layout. Sustain SJ has since asked a New Jersey Superior Court to overturn that approval, arguing that the stormwater plan was inadequate and questioning the zoning and the Planning Board’s authority. On October 21, it separately sent DataOne, Nebius and others a notice of intent to bring a federal Clean Air Act suit. City planning notice · Reporting on the state court complaint · Federal notice of intent
New Jersey lawmakers have proposed limits on new data-center projects. A5482 would pause certain approvals for AI facilities above 10 MW for six months while allowing existing operations to continue. S4659 would pause new construction and permitting pending a state study. For Vineland, any effect would turn on the final law and which permits the expansion still needs. Assembly bill A5482 · Senate bill S4659
The city authorized a five-year payment-in-lieu-of-taxes agreement in January 2026. Nebius projects around 200 permanent on-site jobs once the campus is operating at scale. Nebius project page
Microsoft’s remaining deliveries
The next two deadlines are December 31 and Q2 2027. Nebius expects more Microsoft handovers in November and December as Bloom adds power, bringing cumulative delivery to more than half of contracted capacity by year-end. It has moved the balance into the second quarter of 2027. Nebius November earnings call · November SEC filing
DataOne’s FAQ also gives December 2026 as its target for handing over all 14 halls. That schedule concerns the buildings. For the delayed Microsoft capacity, Nebius still needs enough power, completed fit-out and commissioned clusters. Those are the steps that lead to a customer handover. DataOne project FAQ · November SEC filing
Date or window | Milestone | What was reported or is scheduled |
|---|---|---|
November 2025 and February 2026 | First two Microsoft tranches | Delivered. 2025 annual filing |
Late Q3 2026 | DataOne winds down temporary power | The ramp-down outpaces Bloom’s installation and delays Microsoft deliveries. Nebius earnings call |
October 22, 2026 | First Bloom power block ready | Bloom reports readiness. Nebius confirms the system is supplying power in November. Bloom earnings call · November SEC filing |
Q3 into November 2026 | Further Microsoft tranches | Nebius reports additional deliveries. November SEC filing |
Year-end 2026 | More than half of the contracted Microsoft capacity | Nebius’s revised cumulative delivery target. November SEC filing |
Q2 2027 | Remaining Microsoft tranches | New delivery window for capacity originally scheduled through 2026. 2025 annual filing · November SEC filing |
Why Vineland matters beyond this campus
Vineland put Nebius’s first large U.S. build-to-suit campus to work for Microsoft within a year of the project announcement. It also showed how much a partner’s construction or power decision can affect that customer schedule. Nebius now expects most of its capacity coming online from 2027 onward to come from owned sites, where it can manage permitting, power and fit-out on a single schedule. Vineland is the example management had just given when it explained that shift. Nebius annual filing · November SEC filing
Connect the site to the wider Nebius picture
Compare Vineland’s delivery dates with the rest of the network in the Nebius data-center hub, or open the Vineland record in the Data Center Tracker.
The Nebius model shows how Northwise translates the company’s capacity rollout into revenue.