NBIS Stock Vineland NJ Data Center

Research Note · FreePublished · Updated

Nebius Vineland explained: campus capacity, development phases, Bloom fuel cells, Microsoft contract, permits and the outlook, with tracker and model links.

In this article

DataOne was supposed to keep its temporary generators running until Bloom Energy’s fuel cells could take over at Vineland. New Jersey regulators found that DataOne had been running the gas engines without the required air permits. In late Q3, DataOne began winding down its temporary generation faster than Nebius had planned. Bloom couldn’t replace that power fast enough. Nebius says the gap delayed Microsoft deliveries that had been slated for 2026. Nebius November earnings call · NJDEP enforcement announcement

The old schedule put the Microsoft rollout through the end of 2026. On November 12, Nebius said it expects to deliver more than half of the contracted capacity by year-end. The rest is now scheduled for Q2 2027. Nebius annual filing · November SEC filing

Vineland is already in service for Microsoft. Nebius delivered the first GPU tranche in November 2025 and reported further handovers into November 2026. Bloom is now supplying power as more fuel-cell blocks go in. Nebius annual filing · November SEC filing

Vineland Microsoft delivery schedule. The original rollout ran through 2026. DataOne wound down temporary generation before Bloom could replace it. Nebius now expects more than half of contracted capacity by year-end 2026 and schedules the remaining tranches for Q2 2027.
DataOne’s early generator ramp-down opened a gap in power and pushed the remaining Microsoft tranches to Q2 2027. Bloom fuel cells are now supplying the site.Northwise

The site and the companies behind it

The data center sits at 3963 South Lincoln Avenue in South Vineland, on a former sand-mining property. The land was once earmarked for the Silica Sands golf course. By March 2025, Nebius and DataOne were pitching a purpose-built AI campus expandable to 300 MW. The South Jersey location gave Nebius room to build and a foothold near Philadelphia and the Northeast’s customers. City planning notice · Land-use history · Nebius’s March 2025 announcement

Map of South Vineland, New Jersey, highlighting DataOne’s project parcel, Block 7503 Lot 35.01, near South Lincoln Avenue, Sheridan Avenue and Hance Bridge Road.
The DataOne parcel at 3963 South Lincoln Avenue, using New Jersey’s published tax parcel and road centerline data.Northwise map using New Jersey Office of GIS data

DataOne owns and operates the facility. Northeast Precast is the local construction partner. Nebius installs and runs the servers and networking, and Microsoft buys dedicated GPU capacity from Nebius. Bloom builds, operates and maintains the fuel-cell systems under a separate power agreement. Nebius project page · Fuel-cell agreement filing

New Jersey’s 2020 aerial photograph of South Vineland before the data-center build. An outline marks the later DataOne tax parcel, including cleared ground and surrounding woods.
A 2020 aerial view of the land before the data-center project. The outline marks the parcel later used by DataOne.New Jersey Office of GIS imagery and parcel data. Outline by Northwise.

Current active capacity and planned campus size

Nebius delivered the first Microsoft tranche in November 2025 and the second in February 2026. It reported two deliveries in the month leading up to its August update and further handovers through Q3 and into November. Nebius hasn’t disclosed how many IT megawatts are live or how much capacity each handover added. Nebius annual filing · August shareholder letter · November SEC filing

In August 2025, Nebius put contracted New Jersey power under construction at 200 MW, with 100 MW due in 2025 and another 100 MW in 2026. DataOne later described a 14-hall campus with a maximum of 350 MW. Nebius’s original description was up to 300 MW. The figures come from different announcements, and the companies haven’t reconciled them. August 2025 shareholder letter · DataOne project FAQ · Nebius’s March 2025 announcement

The Bloom contract illustrates the difference between what can be installed and what can be delivered. The agreement calls for about 328 MW of installed fuel cells and about 250 MW of guaranteed power across three phases. Cooling and building systems draw from the site’s power supply alongside the servers. Fuel-cell agreement filing

Figure

Scope

Source

200 MW

Contracted power under construction in the 2025 plan. The schedule called for 100 MW in 2025 and 100 MW in 2026.

August 2025 shareholder letter

Up to 300 MW

Original Nebius campus expansion plan.

March 2025 announcement

Up to 350 MW

DataOne’s later maximum for its 14-hall buildout.

DataOne project FAQ

328 MW installed / 250 MW guaranteed

Expected fuel-cell system and contractual supply across three phases.

Fuel-cell agreement filing

What is actually being built

At its August 17 meeting, the Vineland Planning Board approved a revised two-phase plan. The buildings are a 129,622-square-foot data center and a 587,980-square-foot, two-story expansion attached to it. The notice listed both as under construction at the time. Together they account for just over 717,000 square feet of data-center space in a much larger development. City planning notice · August 17 meeting minutes

Much of the rest of the site is devoted to keeping those halls powered and cooled. The approved plan includes four ground-mounted Bloom fields and five multistory power structures, a 92,466-square-foot chiller building, LNG storage and filling equipment, a 6,750-square-foot water-treatment plant and 161,896 square feet of Megabay structures. City planning notice

The city’s amended site plan shows a 129,622-square-foot Phase 1 data-center building and a 587,980-square-foot Phase 2 expansion. Phase 2 also includes Bloom power areas, a chiller building, water treatment, LNG facilities and Megabay structures.
The amended site plan approved August 17, 2026. The two data-center buildings account for 717,602 square feet, with power, cooling, water and other structures listed separately.Northwise diagram based on Vineland Planning Board records

Why the power strategy is central to the project

Vineland was designed to make most of its electricity on site, so DataOne could build its power supply alongside the halls. Nebius signed its agreement with Bloom in May 2026 to replace the planned reciprocating engines with solid oxide fuel cells. Both systems use natural gas. The fuel cells use an electrochemical reaction to generate electricity, and the approved design includes on-site LNG storage. Nebius and Bloom announcement · City planning notice

Power design showing natural gas feeding Bloom fuel cells, which supply the data halls and cooling. The three-phase agreement specifies about 328 MW installed and 250 MW guaranteed. DataOne’s design assigns grid backup to critical network equipment.
DataOne’s permanent power design. Bloom supplies the halls and their cooling systems, and the utility grid is designated as backup for critical network equipment. The MW figures come from Nebius’s three-phase fuel-cell agreement.Northwise, from the May 2026 fuel-cell filing and DataOne’s project FAQ

Nebius infrastructure chief Andrey Korolenko said DataOne’s engines were meant to cover the period when only part of the Bloom system would be ready. By winding down early, DataOne took away power Nebius had counted on for new Microsoft capacity. Bloom reported that its first block was ready on October 22. By the November call it was supplying the site and Nebius was accelerating the installation of the remaining blocks. Bloom earnings call · Nebius November earnings call

DataOne’s FAQ lists a 5 MW municipal supply and describes a proposed 49 MW feed from Atlantic City Electric. The design assigns the grid a backup role for critical network equipment, with Bloom supplying the halls and mechanical systems. DataOne project FAQ

Power economics and the cost of getting the timing wrong

The Bloom agreement buys power as a service. Bloom installs, operates and maintains the equipment, while Nebius pays for capacity and electricity. The filing describes three expected phases with a ten-year supply term for each and up to $2.6 billion in service fees over the life of the agreement. Fuel-cell agreement filing

Bloom separately described a $1.7 billion project investment with financing and development support from Industrial Development Funding, Oaktree, Morgan Stanley and MUFG. That financing supports the power assets. Nebius is paying to run compute against the supply, while Microsoft’s payments depend on the delivery and availability of the GPU service. A delay pushes back the point when a new cluster can contribute revenue. Bloom project financing · Nebius annual filing

The computing and cooling inside the campus

The GPUs run in clusters, with networking, storage and cooling commissioned before Nebius can hand them over to Microsoft. Vineland’s cooling design calls for a one-million-gallon initial fill, then recirculates water in a closed loop. The chillers are housed indoors to reduce noise, and the site plan includes a water-treatment plant. At the August hearing, residents and experts raised questions about drainage and groundwater on the former mining property. Nebius project page · August 17 meeting minutes

What Microsoft brings to Vineland

Microsoft signed for five years of dedicated GPU capacity at Vineland, delivered in tranches. Nebius put the base agreement at about $17.4 billion through 2031, with additional capacity and services potentially taking it to about $19.4 billion. The annual filing estimates about $6.96 billion in aggregate upfront payments and monthly billing for the rest over the service terms of each tranche. Microsoft agreement SEC filing · Nebius annual filing

Microsoft’s base Vineland GPU contract is about $17.4 billion, including about $6.96 billion in estimated upfront payments. The balance is billed monthly by tranche. Optional capacity and services could bring the total to about $19.4 billion.
How Nebius structured the Microsoft agreement. The base value includes about $6.96 billion in estimated upfront payments. The balance is billed over each tranche’s service term. Optional services and capacity can bring the total to about $19.4 billion.Northwise, from Nebius’s 2025 annual report and September 2025 Form 6-K

The contract gave Nebius a customer to build around and a way to fund some of the GPU deployment. When Nebius announced the deal, it planned to use Microsoft cash flows and borrowing secured against the agreement. Microsoft can receive service credits or terminate individual tranches under specified delivery or availability conditions. Contract announcement · Nebius annual filing

Nebius’s August letter said it had “delivered all capacity tranches to Microsoft” and mentioned two deliveries in the preceding month. The November filing shows the rollout continued beyond that update, with new handovers and more capacity still due. August shareholder letter · November SEC filing

Local approvals, temporary generators and community concerns

In September, NJDEP assessed a $1.072 million penalty over 62 natural-gas engines installed and operated without preconstruction permits or operating certificates. The engines were rated at 1,982 kW apiece, roughly 123 MW of installed generation across the fleet. The agency cited the equipment DataOne had used to supply the site during the transition. NJDEP enforcement announcement

DataOne asked for an administrative hearing and a stay on October 9, challenging the state’s permit determination and penalty. The original 45-day period ran to November 6. State senator Michael Testa asked NJDEP for an update on November 9. Whether the stay was granted or the remaining engines were permitted is still open in the public record. Clean Air Act notice, pp. 8–9 · Testa’s letter to NJDEP

The August planning vote approved the revised building and power layout. Sustain SJ has since asked a New Jersey Superior Court to overturn that approval, arguing that the stormwater plan was inadequate and questioning the zoning and the Planning Board’s authority. On October 21, it separately sent DataOne, Nebius and others a notice of intent to bring a federal Clean Air Act suit. City planning notice · Reporting on the state court complaint · Federal notice of intent

New Jersey lawmakers have proposed limits on new data-center projects. A5482 would pause certain approvals for AI facilities above 10 MW for six months while allowing existing operations to continue. S4659 would pause new construction and permitting pending a state study. For Vineland, any effect would turn on the final law and which permits the expansion still needs. Assembly bill A5482 · Senate bill S4659

The city authorized a five-year payment-in-lieu-of-taxes agreement in January 2026. Nebius projects around 200 permanent on-site jobs once the campus is operating at scale. Nebius project page

Microsoft’s remaining deliveries

The next two deadlines are December 31 and Q2 2027. Nebius expects more Microsoft handovers in November and December as Bloom adds power, bringing cumulative delivery to more than half of contracted capacity by year-end. It has moved the balance into the second quarter of 2027. Nebius November earnings call · November SEC filing

DataOne’s FAQ also gives December 2026 as its target for handing over all 14 halls. That schedule concerns the buildings. For the delayed Microsoft capacity, Nebius still needs enough power, completed fit-out and commissioned clusters. Those are the steps that lead to a customer handover. DataOne project FAQ · November SEC filing

Date or window

Milestone

What was reported or is scheduled

November 2025 and February 2026

First two Microsoft tranches

Delivered. 2025 annual filing

Late Q3 2026

DataOne winds down temporary power

The ramp-down outpaces Bloom’s installation and delays Microsoft deliveries. Nebius earnings call

October 22, 2026

First Bloom power block ready

Bloom reports readiness. Nebius confirms the system is supplying power in November. Bloom earnings call · November SEC filing

Q3 into November 2026

Further Microsoft tranches

Nebius reports additional deliveries. November SEC filing

Year-end 2026

More than half of the contracted Microsoft capacity

Nebius’s revised cumulative delivery target. November SEC filing

Q2 2027

Remaining Microsoft tranches

New delivery window for capacity originally scheduled through 2026. 2025 annual filing · November SEC filing

Why Vineland matters beyond this campus

Vineland put Nebius’s first large U.S. build-to-suit campus to work for Microsoft within a year of the project announcement. It also showed how much a partner’s construction or power decision can affect that customer schedule. Nebius now expects most of its capacity coming online from 2027 onward to come from owned sites, where it can manage permitting, power and fit-out on a single schedule. Vineland is the example management had just given when it explained that shift. Nebius annual filing · November SEC filing

Connect the site to the wider Nebius picture

Compare Vineland’s delivery dates with the rest of the network in the Nebius data-center hub, or open the Vineland record in the Data Center Tracker.

The Nebius model shows how Northwise translates the company’s capacity rollout into revenue.

Northwise Research

Get Northwise Research in Your Inbox

New research, model releases, portfolio updates, and major Northwise developments delivered directly to your inbox.

Reader discussion

Discuss the research

0 published

Create a Free account to join the discussion with a display name.

Create a Free Account

No comments yet. Start a thoughtful discussion.