Nebius India Data Centers

Nebius plans to open its first two Asia-Pacific data centers in India in 2027.

Research Note · FreePublished
In this article

The first Indian site could be running customer workloads in the first half of 2027. For that to happen, a partner would need to hand over a hall with power and cooling early in the year, and Nebius would need GPUs ready to install. Nebius gives a full-year target for both sites and has yet to name a launch quarter for either. [1] [2] [3] [4]

The best public trail leads to Hyderabad and Chennai. In Hyderabad, Nebius has been recruiting the engineers who install GPU clusters and decide when operations can take them over. In Chennai, it wants someone on the receiving end of the truck, an on-site specialist to take delivery of GPU racks, servers and spare parts and put them in engineers’ hands. [4] [5] [6]

One prospective landlord, CapitaLand, was targeting year-end 2026 for buildings in both cities. In late October its Hyderabad building and first-phase mechanical and electrical works were nearing completion. Chennai’s shell was still under construction, although another operator already had halls running in that city. The identity of the host could decide which opens first. Nebius has yet to name its landlords or say how many megawatts it will take. [2] [3] [1]

Paris shows how quickly Nebius can move once it has the room and the hardware. On September 25, 2024, it named Equinix as its Paris host and said it was already setting up servers. By November 19 it reported deploying the first customer workloads there, less than eight weeks later. Nebius is recruiting for that work in India. It has yet to announce that it has taken possession of a powered hall or started installing racks there. [7] [8] [6] [4]

India timing. Two colocations targeted in 2027. A first-half first workload is a conditional Northwise scenario. The second site has no announced quarter.
The early window depends on a tenant-ready hall, GPU delivery and cluster acceptance. Nebius has given one calendar-year target covering both sites.

Selling cloud before building a region

Nebius announced its Asia-Pacific expansion in March. By November it had signed customer agreements across India, South Korea, Japan, Australia and Singapore. India is where management chose to put the first physical capacity. A customer can sign with Nebius well before the company has a rack in that customer’s country. The commercial footprint was already bigger than the deployment footprint. [9] [1]

Colocation gives Nebius a way into that market while it builds much larger campuses in the US. An Indian operator can supply a building, power and cooling. Nebius can install the computing equipment, run the cloud and sell it through the same platform its customers already use. Indian customers with latency-sensitive applications would gain a closer place to run them. Customers who need workloads to stay in India would have a local option once Nebius publishes the region and its service terms. [10] [11]

At the Bengaluru Tech Summit on November 17, AI Spectrum India reported that a Nebius representative outlined plans to bring NVIDIA Vera Rubin systems to India. That gives the expansion a potential hardware generation. The company has yet to disclose a rack count, shipment or allocation between the two sites. Bengaluru was the venue for the announcement. [12] [13]

Southern India map showing Hyderabad inland, Chennai on the coast and Bengaluru to its west.
Hyderabad and Chennai are the two city leads. Bengaluru hosted the November summit. Markers indicate city centers. Coastline from Natural Earth.

Hyderabad has the longer paper trail

Hyderabad sits inland on the Deccan Plateau. The city already has two very different routes to more computing capacity. In Madhapur, developers can build into an established technology district near enterprise customers. At Bharat Future City, south of the city, the state is trying to create an entirely new cluster. Both places appear in the debate over Nebius. Their construction timetables tell different stories. [14] [15]

In its July 20 issue, the Indian infrastructure trade publication Project Reporter listed Nebius by name against a Hyderabad AI data center. Row 41 on page 22 classified it as conceptual or in planning. The entry gave no operator, power figure or underlying source. Its value is that someone was reporting a Hyderabad project months before the shareholder letter. The publication gives readers no way to establish whether its information was independent of the hiring already underway. [16]

The jobs add substance. A September field engineering position covers checking power and cooling, supervising rack installation and testing hardware before delivery. An October technical project manager position owns the handover from the project team to operations. Both carry Hyderabad locations. The field engineer travels, so the city could also serve as a base for more than one deployment. Our read is that Hyderabad is a strong location for Nebius’s Indian deployment team and a likely site for one of its first halls. [4] [5]

Why CapitaLand is worth watching

CapitaLand India Trust owns a project in International Tech Park Hyderabad in Madhapur. Its October 28 Singapore Exchange filing gives it 42 MW of gross power and 27 MW of IT load at full design. The trust said the building shell and first-phase mechanical and electrical works were nearing completion, with building completion targeted for the fourth quarter of 2026. That is a credible starting point for a tenant trying to deliver servers in 2027. [2] [14]

There is a reason to examine this operator beyond the calendar. In July, The Economic Times named Nebius among six neocloud companies exploring Indian capacity and CapitaLand among five operators involved in discussions. The report did not pair individual buyers and sellers. CapitaLand’s filing actually identifies leasing progress for its Mumbai towers. The Hyderabad and Chennai columns describe construction. CapitaLand is the strongest two-city timing match in the records we found. The identity of its tenants remains an open question. [17] [2]

CapitaLand designs compared. Hyderabad has 42 MW gross and 27 MW IT, Chennai 53 MW gross and 34 MW IT.
Gross power covers the whole facility. IT load is the share designed for servers and other IT equipment. Both figures belong to the developer.

Where the VOLT story breaks down

VOLT has a genuine relationship with Nebius. Its CEO confirmed an agreement for a project in Rotterdam. VOLT also has a Hyderabad project with UPC Renewables. Telangana’s January memorandum describes a 100 MW AI data center at Bharat Future City and a separate 100 MW renewable power plant. The proposed investment spans five years. [18] [15]

A widely shared investor post assigned an initial 29 MW and eventual 129 MW to Hyderabad. VOLT’s own portfolio puts 29 to 129 MWe in Dubai. Its Hyderabad entry says 150 MWe and targets a 2027 construction start. The state’s 100 MW proposal and the developer’s 150 MWe figure come from different descriptions. Neither is a disclosed allocation to Nebius. [19] [20] [15]

That calendar makes VOLT a weaker fit for an initial opening. Nebius wants customers running in 2027. VOLT plans to start building in 2027. A phased delivery or an existing hall elsewhere could change the picture, but the public VOLT schedule gives no date for handing a Hyderabad hall to a tenant. [1] [20]

Chennai has the more revealing job description

The first Chennai lead was easy to overread. A field leadership job appeared under both Chennai and Hyderabad, but the postings shared one internal requisition. On October 30, Nebius opened a different job with its own requisition and Chennai, Tamil Nadu as its sole listed location. [21] [6]

The warehouse specialist works on site. The person receives hardware, stages equipment for rack deployments and issues parts to data center engineers. Travel to another location is occasional. A field engineer can be based in one city and commission racks across a region. The Chennai specialist is expected to work wherever the stock arrives. That makes Chennai the strongest first-party clue to a physical site in the public record. Nebius has yet to say when those deliveries begin. [6] [4]

Concept illustration of equipment being moved across a receiving dock.
Northwise concept illustration of the work in the Chennai job description. Nebius has yet to report a rack delivery there.

Chennai has an advantage Hyderabad cannot reproduce inland. International subsea cables come ashore here. Ambattur, west of the center, already has an industrial cluster suited to data halls. In October, CapitaLand unveiled its Chennai 01 building there. Its subsequent exchange filing still described shell works in progress and a fourth-quarter completion target. The design calls for 53 MW gross and 34 MW of IT load. An unveiling and a tenant’s first day of service can be months apart. [14] [22] [2]

ST Telemedia Global Data Centres offers another path. In February, STT reported 40 MW already operating at its Ambattur campus and broke ground on Chennai 4 there. At its separate Siruseri campus, it had opened a 7.2 MW first phase of a 45 MW design. Existing power and buildings make such campuses worth examining for a faster move-in. Neither the operating figures nor the campus designs tell us how much space is available to Nebius. [3]

In December 2025, Tamil Nadu’s environmental authority approved STT’s revised building description, including IDC 4, and a built area of about 110,688 square meters. It declined a requested reduction in the site area. The applicant was STT. The order shows exactly what a researcher can learn from a local filing about the building, even when it says nothing about who will rent the racks. [23]

An excerpt from STT’s Tamil Nadu clearance approving a revised built area of 110,688.46 square meters.
The Tamil Nadu authority approved this building-area change at STT’s Ambattur property. Source document, page 2.

The municipal records turn up other buildings on a similar timetable. Chennai’s planning authority approved eight floors of data center space for Web Werks Infra2 in Ambattur and forwarded the decision to the city for a building permit. Iron Mountain markets a phased Ambattur campus beginning in 2026. That concentration of projects makes the Chennai hiring lead more credible and an exact address harder to infer. [24] [25]

The water dispute and the tax incentive

Telangana has a real dispute over who should get water and power. On October 27, the Human Rights Forum asked the state to suspend existing hyperscale AI commitments and refrain from making new ones until independent studies establish the impact on drinking water, agriculture and electricity supply. I found the original demand and no government order imposing the requested statewide pause. A Future City development awaiting construction has more approvals and utility work exposed to that debate than an already serviced hall. A tenant moving into the latter still needs enough power and cooling for its own racks. [26] [15] [27]

India’s environment ministry explained to Parliament in August that the building or development can trigger an environmental clearance even when the data center activity itself does not. State pollution boards oversee water and air requirements. That distinction helps explain why a search for “Nebius” in a permit portal can miss the right site. It also helps rule out false leads. Hyderabad’s HYD 04 application at Shadnagar explicitly names Microsoft Corporation (India) as its proponent. Microsoft’s US business with Nebius supplies no link to that Indian project. [28] [29]

National tax policy gives foreign cloud providers another reason to look at India. A conditional exemption can run through March 31, 2047 for qualifying income from procuring specified Indian data center services. The August amendment allows the Indian operator to own or lease the center. Other conditions remain, including an Indian reseller for sales to Indian users and restrictions on the foreign company owning or operating resources of the specified center. For a provider that intends to install its own GPUs, the ownership provisions deserve a close reading before anyone pencils in a tax saving. Nebius has disclosed no India-specific benefit to put into a margin forecast. [30] [31]

When customers could actually use the sites

For the first site, the date that counts is when a customer can run a workload on an accepted GPU cluster. If Nebius takes a ready hall early in 2027, delivery in the first half is plausible. If its host is still commissioning power or cooling in the spring, or the racks arrive later, the first workloads could land in the second half. For the second site, the only public window is January through December 2027. Nebius has announced neither the sequence nor the interval between openings. [1] [2] [4] [5] [8]

For an investor following Nebius’s move toward owned campuses, India illustrates why colocation still earns a place in the network. The company can lease its first two halls in Asia-Pacific while building much more of its US capacity itself. The payoff would be the ability to serve regional customers earlier. The exposure is that someone else still has to deliver the building, electricity and cooling on time. [1] [10]

The figure to carry into the 2027 outlook is two planned colocations. The figures to wait for are Nebius’s own contracted and operating megawatts. An operator’s 27 MW data hall, a developer’s 150 MWe campus and a country’s tax incentive are three different things. Only a tenant allocation and delivery schedule will tell us what India contributes to Nebius’s ramp. [1] [2] [20]

Follow the network in the Northwise Nebius data center hub, explore the Data Center Tracker, or compare delivery assumptions in the Nebius models.

Track the two city leads in Hyderabad and Chennai.

Sources

1. Nebius Q3 shareholder letter, SEC exhibit

2. CapitaLand India Trust, October 28 SGX filing, slides 6 and 29

3. STT GDC’s Chennai opening and expansion

4. Nebius field deployment engineer, Hyderabad

5. Nebius technical project manager, Hyderabad

6. Nebius warehouse logistics specialist, Chennai

7. Nebius begins setting up its Paris cluster at Equinix

8. Nebius reports deploying the first Paris customer workloads

9. Nebius announces its Asia-Pacific expansion

10. Nebius’s requirements for infrastructure providers

11. Nebius AI Cloud region directory

12. AI Spectrum India’s Bengaluru Tech Summit dispatch

13. Bengaluru Tech Summit exhibitor directory, printed page 137

14. Mitsui Fudosan’s investment and property schedule

15. Telangana’s January 22 UPC and VOLT memorandum

16. Project Reporter, July 20 issue, page 22, row 41

17. The Economic Times on Indian colocation talks

18. ANP interview with VOLT’s CEO on Rotterdam

19. Retail discussion and its original citations

20. VOLT’s Hyderabad and Dubai project specifications

21. Nebius public Greenhouse board

22. CapitaLand’s October 15 Chennai unveiling

23. Tamil Nadu environmental clearance amendment, file 12753

24. Chennai Metropolitan Development Authority planning order

25. Iron Mountain’s Chennai campus

26. Human Rights Forum’s October 27 request to Telangana

27. NITI Aayog’s October data center evaluation framework

28. Environment ministry’s August 6 answer to Parliament

29. Telangana environmental application for Microsoft HYD 04

30. Finance Act 2026, Schedule IV

31. Taxation and Other Laws (Amendment) Act 2026, section 4