Nebius Independence Data Center
Nebius has 1.1 GW contracted at its Independence, Missouri data center. Follow the first building, the utility power plan and the 2027 deployment target.
In this article
Just northeast of Missouri Route 78 and Little Blue Parkway, the sale of 398 acres at Eastgate turned an old industrial development plan into a place for Nebius to build its own U.S. computing campus. On Bly Road, the work has already split into two distinct jobs. One permit covers the electrical switchyard. The other covers the interior of the first data center building. That’s how a four-building, 1.2 GW campus begins to take shape. Eastgate records · October permits
Nebius’s November shareholder letter added 300 MW to the Missouri power story and put the site at 1.1 GW under contract. It also kept Missouri in the group of owned sites expected to deploy capacity in 2027. The first step is much smaller than either gigawatt figure. Independence Power & Light has to deliver permanent service to the campus, and Nebius has to commission the first building and get it ready for customers. The permits show both workstreams moving. The date and size of first permanent delivery remain unconfirmed. Nebius Q3 letter · Campus project page
How Eastgate became a Nebius campus
Eastgate sits in the Little Blue Valley on the eastern side of Independence, in the Kansas City metro. The city had already zoned the land for industrial and business park uses. NorthPoint Development sold the tract to Nebius in December 2025 and kept responsibility for rerouting the southern stretch of Bly Road. After winter public meetings and a March 2 vote on development incentives, Nebius and its Phase 1 contractor, ARCO National Construction, marked the start of construction on May 12. City project FAQ · Nebius groundbreaking

The city’s first presentation in December described up to ten buildings. By January, the project team was showing a four-building master plan, with a one-story first building and three proposed two-story buildings. Nebius now describes a five-to-seven-year construction program. Its Kansas City-area operations and the separate Patmos project elsewhere in Independence have their own schedules. The Eastgate numbers belong to this campus. December city presentation · Patmos project page

A 300 MW expansion, 1.1 GW under contract and a 1.2 GW design
Start with what management actually disclosed. The November 12 shareholder letter reported a 300 MW expansion and 1.1 GW under contract at the Missouri site. Those are an increase and the resulting contracted total, respectively. That implies an earlier contracted base of about 800 MW at the precision Nebius reported. The company’s local project page also describes an 800 MW utility supply plan, but the Q3 letter gives no counterparty or phase for the 300 MW and does not identify the underlying agreements. Q3 shareholder letter · Local power plan
The 1.2 GW figure is the full campus design. Nebius describes it as 800 MW through the municipal utility and up to 400 MW of possible future generation on the campus. The local page still puts that on-site power solution under evaluation. The disclosure leaves open how much of the new contracted amount comes from each route, and whether the older design split will hold. The gap of 100 MW between the design and the reported total does not establish an uncontracted 100 MW block.

The city also describes a 300 MW reserve requirement in its account of the utility arrangement. Reserve capacity gives the utility a cushion under regional reliability rules. The city’s reserve reference and Nebius’s 300 MW expansion are separately sourced, and the public disclosures give no basis for treating them as the same block. The 200 MW in the older technical presentation is an initial utility delivery target. The amount of active IT load, commissioned customer capacity and site-specific revenue remain undisclosed. City utility FAQ · Technical presentation, page 8
Two properties and one municipal utility
The campus and Blue Valley are different properties. Independence Power Partners is developing the former Little Blue Valley coal plant site as an off-site source of grid power. Independence Power & Light, or IPL, serves the campus and participates in the Southwest Power Pool, the regional grid operator. The city’s December 2025 update records two generation purchase agreements between IPL and Independence Power Partners, along with a separate energy services agreement under which IPL serves Nebius. All were executed on December 5. Eastgate power agreements
The city planned for the first building to need power before the new turbines at Blue Valley were ready. On January 20, the council approved four purchases of accredited regional grid capacity from NextEra Energy Marketing and Evergy Kansas Central. The minutes describe a bridge from June 2026 to June 2027, when the city then expected the plant to come online. The purchases give IPL a way to meet its supply commitment. A dated service notice from IPL or Nebius would establish when the campus itself first took permanent power. January 20 council minutes, ordinances 19774 through 19777.

At Blue Valley, Missouri’s Department of Natural Resources issued construction permit 072026-012 for Independence Power Station 1 on July 31. The permit covers 15 Solar Titan 130 natural-gas turbines with a combined nominal gross output of approximately 267.5 MW under the stated rating conditions. The city’s earlier Eastgate update used an estimate of 225 MW for the first generation phase. The permit narrows what equipment can be built and sets testing, emissions and operating requirements. Useful power from the completed plant will depend on commissioning and grid availability. Missouri DNR permit
What the permits show on Bly Road
The October building report lists two separate commercial permits as issued. The switchyard is $10.4 million in registered permit value. The Phase 1 interior work is about $27.0 million. One is the work that lets power enter the campus. The other is where electrical, mechanical and computing infrastructure can start turning an industrial shell into a usable data center. The amounts are permit valuations for those jobs. City permit report, page 1

In January, the technical presentation targeted 200 MW of initial utility service in late Q3 2026. Nebius’s project page still gives the broader second-half 2026 window. The November 19 utility board agenda included a data center update, but its packet has no written service date or MW handover for Eastgate. The permit record establishes permission to build the switchyard. A permanent service notice, energization record or a dated disclosure from IPL or Nebius would establish first power. November utility board packet · Nebius project timeline
What could come online in 2027
In April, Nebius public affairs vice president John Sutter described a single-story first building at the north end of the site and estimated it could begin serving customers around Q3 2027. He expected the roof by year-end 2026, followed by months of internal work. Local coverage at the May groundbreaking reported an earlier Q2 estimate. Those spring dates give a sense of the working schedule. The company’s November shareholder letter still includes Missouri among the owned sites expected to deploy in 2027 and gives no Missouri quarter or usable MW figure. Sutter’s April interview · May groundbreaking coverage · November shareholder letter

Management says it has secured the power and components it plans to bring online across its 2027 portfolio. At Independence, the work still runs through the first building. Crews can fit out the interior while utility work continues. Permanent power is what lets the team complete testing of electrical and cooling systems and bring customer clusters into service. A first customer ramp later in 2027 remains plausible on the public evidence. Its size depends on how much power the first building can draw and how quickly the halls clear commissioning.
Later buildings need their own power and acceptance sequence. The January presentation described a study for another 600 MW of utility supply in early 2029, and the live company page still refers to an additional-power study for that period. The local project page gives a longer, phased construction horizon. The date to watch for later phases is when firm utility or on-site power is tied to a specific building and a service window. Utility study timetable
Cooling, backup and bringing GPUs online
Nebius plans a closed-loop mechanical system that circulates water through the cooling equipment. Its project page estimates about one million gallons for an initial fill per 200 MW of system capacity and lists 400,000 to 640,000 gallons a year for staff and process support. The earlier technical presentation used a 1.4 million gallon annual estimate. Those figures come from different stages of design, and the public descriptions do not provide a common scope for comparing them. Operating withdrawals and discharge records will show what the built system actually uses. Current project design · January technical estimates
Nearby homes make the equipment layout consequential. Nebius says the loudest equipment is placed toward the site’s interior and describes barriers and low-noise fans. It also anticipates emergency generators with sound enclosures and containment. Backup helps the halls ride through outages. Any permanent on-site generation would have a different duty cycle, emissions profile and permitting path.
Owning the buildings gives Nebius control over the electrical, cooling and network design it will reuse across GPU generations. The first customer clusters will still need a powered fit-out, functioning network links and acceptance testing. The public record leaves the Phase 1 rack count, hardware mix, carrier routes and customer allocations open. Those are the details that would let investors translate the electrical ramp into usable compute. Nebius on owned infrastructure
The tax deal, neighborhood and approvals
On March 2, the council voted 5–2 to approve the Chapter 100 development plan. Ordinance 19791 authorizes two series of taxable industrial development revenue bonds with a combined maximum of $150.632 billion. The figure is an authorization ceiling covering real estate and equipment. Actual spending depends on what Nebius builds and buys. The city’s description of Chapter 100 explains that the city holds legal title under the lease structure and the developer pays the amounts the agreements specify. March 2 council record, Ordinance 19791
The city says Nebius pays for its power and required infrastructure. It describes advance billing, financial guarantees, provisions for grid curtailment, and the right to revisit later-phase terms if costs rise. Nebius also announced training and education commitments, including work with Metropolitan Community College. The benefits depend on construction, actual employment and the local payments specified for the project. City terms and protections · Nebius community commitments
Bly Road shows how a campus schedule can collide with daily life. The city reopened it to residents and other local traffic on November 6 while NorthPoint finished signals, sidewalks and markings. The city expects full reopening in early December, after the remaining work and inspections. That is a road milestone with its own contractor and dependencies. November 6 city notice
The city explicitly excluded the existing Nebius project from its July 180-day pause on new data center and battery-storage applications. On October 5, the council also adopted new zoning standards for those uses. Eastgate’s exclusion from the July pause leaves the normal approvals in place for work the campus undertakes. An expansion beyond the approved plan or future on-site generation can bring separate filings. City moratorium notice · October 5 council record, Ordinance 19850
Residents and the Independence GUARD Alliance challenged the project in court. On October 31, The Examiner reported that the residents had withdrawn their request for a temporary restraining order. Their attorney said the Missouri Sunshine Law claims could still affect construction. The latest ruling on those underlying claims remains unconfirmed. The Examiner’s October 31 account.
Why Independence matters to the Nebius buildout
Independence is the first time Nebius has taken on a U.S. campus at this scale. A company that leases a hall can start serving customers sooner when a partner has space and power ready. At Eastgate, Nebius gets to decide how the buildings, power systems and interconnect fit together and when to commit capital to the next phase. It also takes on the work of coordinating utility delivery, construction and customer handover. Blue Valley and IPL show how much coordination an owned campus still needs outside its property line.
Management expects owned sites to make up most new capacity from 2027 onward. The October $3.5 billion Citi facility gives Nebius financing for data-center development, GPU procurement and corporate uses across the business. The company has given neither a facility allocation nor a customer commitment specific to Independence. For the 2027 model, the meaningful change comes when a specific block can begin serving customers. A larger contractual power position helps make later phases possible. It takes acceptance and time in service for that position to show up in Missouri revenue. Citi facility announcement · Updated capacity outlook
Follow the campus through permanent IPL service, first-building commissioning and customer availability. Those three milestones will make it possible to be more precise about active capacity and how much of its first year Independence can contribute.
Open Independence on the Data Center Tracker · See the full Nebius site hub · Explore the Nebius model and valuation
Reader discussion
Discuss the research
Create a Free account to join the discussion with a display name.
Create a Free Account




No comments yet. Start a thoughtful discussion.