IREN Stock Analysis | Is It a Buy After the November Selloff?
We compare IREN’s November 20 close of $11.82 with our 2027 price target and show how AI cloud revenue, debt and dilution change what each share is worth.
In this article
What changed for IREN shareholders at $11.82?
IREN shares fell from $21.64 on November 6 to $11.82 on November 20. By then Microsoft had already accepted the first hall IREN built for it in West Texas. The former bitcoin miner had turned a grid connection into a working AI cluster that we estimate earns about $485 million a year under the Microsoft agreement. The selloff made a different question more urgent for investors. How much of the next hall would each share own once IREN had paid to build it? Horizon 1 acceptance announcement

Our November 8 forecast had IREN selling about $5 billion of stock during 2027. At $11.82, that would take roughly as many new shares as the company starts the year with. The halls could open on schedule and an existing shareholder would still own far less of their earnings. Read our original 2027 IREN stock forecast · IREN’s 2027 model page
We think IREN has a better chance of borrowing against its contracts than the November selloff suggests. Microsoft prepaid 20% of its contract. Another customer recently agreed to prepay 90% of its GPU cost to secure five years of capacity. Those buyers care enough about getting access on time to help pay for the equipment. Our base case gets IREN through 2027 without selling common stock to pay suppliers. It depends in part on two loans IREN still needs to secure, $2 billion against its data centers and a $3 billion corporate credit line.
IREN’s free 2027 financial model
Our base case puts 743.3 IT megawatts into paid service by December 31. They support $12.99 billion of annualized revenue at year-end, although IREN earns $5.86 billion during 2027 itself. Those numbers can coexist because so many of the best-priced halls open in the fourth quarter. The harder part is finding the cash for $26.85 billion of capital spending while those halls are still being built.

IREN’s 2027 AI capacity in Texas and British Columbia
IREN began by using cheap, connected power to mine bitcoin. Its September 2026 quarter shows how far the business has moved. AI cloud generated $200 million of its $228 million of revenue. Mining contributed $28 million. At quarter-end, 93 IT MW were operating and AI cloud revenue was running at about $1 billion a year. Behind that stood $20.3 billion of contracted backlog, including $9.6 billion from Microsoft and $3.4 billion from NVIDIA. IREN’s quarterly results

For 2027, five sites do the work. Childress contributes 525 GPU-equipped IT MW in our base case, Sweetwater 1 adds 200 and three British Columbia sites supply 130. Existing connections give the Canadian sites an advantage: Prince George can add 5 IT MW and Mackenzie 10 within their power limits. Canal Flats contributes 20 and is already counted in that 130. Galicia has development potential, but we have yet to see an IREN GPU order or compute customer there. We removed the 5 MW of Spanish capacity in the original base. The rest of IREN’s power portfolio can support future contracts without contributing a dollar to this forecast. IREN infrastructure guide
When installed GPUs start billing at Sweetwater
A site’s grid connection tells you how much power can enter the property. Cooling and electrical losses take a share before the rest reaches the computers. At our assumed power usage effectiveness of 1.25, a 50 MW grid connection supports 40 IT MW. Even after that equipment is installed, the operator has to qualify the cluster and the customer has to accept it. That is when billing begins.

Sweetwater makes the distinction visible. In our base case, blocks C and D can each accommodate 50 IT MW by year-end. Customers start taking service on December 29. With three days of a 30-day acceptance ramp behind them, each block exits the year billing 5 MW. Those two halls account for 90 MW of the 111.7 MW still awaiting acceptance across the company. Horizon 6 at Childress accounts for the other 21.7 MW. A few weeks at either site are worth far more to the December run rate than to the income already earned that year.
Microsoft’s four Horizon halls and the first wave of AI contracts
Microsoft’s four Horizon halls at Childress account for 200 IT MW. Horizon 1 is already earning. By the November update, Horizon 2 had power to the racks, installed GPUs and fiber. Horizon 3 had GPUs on site and three halls energized. Horizon 4 received its equipment later. That progress is why we expect the remaining blocks to enter service in stages from mid-January through February. Microsoft had requested a network redesign, and IREN said the change carried no delay credits.

The initial program also includes Prince George, Mackenzie and the first Childress air-cooled deployment. We estimate 332.5 IT MW across all seven blocks, compared with management’s rounded 0.3 GW. Once accepted, they earn about $4 billion a year. Roughly $3 billion of that run rate sits in the unfinished blocks. If they all slip a month, roughly $250 million of revenue moves out of calendar 2027.
Microsoft pays about $9.7 million per IT MW each year. That is the lowest price among these contracts and one reason the next stage can happen at all. A lender can advance money against five years of payments from Microsoft on better terms than against a short booking with a less established buyer. IREN has obtained GPU financing at about 6% against investment-grade contracts, compared with 9% to 9.5% on recent financing backed by lower-rated customers.
NVIDIA deliveries and the next halls at Childress and Sweetwater
NVIDIA has contracted for 60 MW of gross power at Childress. We translate that into 45 IT MW, with three 15 MW deliveries in March, June and September. Its five-year agreement adds about $680 million of annual revenue at full delivery. IREN also has a commitment to an existing frontier-lab customer whose terms remain private. We allow 50 IT MW from May at $21 million per MW. Together with the initial contracts, those reservations take 427.5 IT MW before IREN can sell a single additional megawatt at new prices. NVIDIA agreement

Second-wave block, Base case | IT MW | GPU status | Billing begins | Contract basis |
|---|---|---|---|---|
NVIDIA tranches 1 to 3 | 45 | Ordered | March, June, September | Signed, $15.1M per IT MW |
Childress air, existing-customer reserve | 50 | Ordered | May | Committed, terms undisclosed |
Childress air, new sales | 92.5 | Ordered | June to November | New contracts |
Horizon 5 | 50 | Ordered | Late October | New contracts |
Sweetwater 1, block A | 50 | Ordered | Late October | New contracts |
Sweetwater 1, block B | 50 | Partly ordered | Late November | New contracts |
Horizon 6 | 50 | To order | Mid-December | New contracts |
Sweetwater 1, blocks C and D | 100 | To order | Late December | New contracts |
Canal Flats | 20 | To order | Late November | New contracts |
IREN said it had ordered GPUs for about 0.3 GW of its next 0.5 GW. The company gave the total. Our allocation follows construction progress: the Childress air halls first, then Horizon 5, Sweetwater A and part of Sweetwater B. Horizon 5 and 6 already had completed substations. At Sweetwater, the first two halls had finished foundations and work was under way on structure and cooling. The later two were earlier in construction. That is why the delivery calendar bunches up in the fourth quarter.
Texas had also resumed normal environmental permit review by November 17, when the Texas Commission on Environmental Quality confirmed the change. ERCOT’s separate process still matters. Both Sweetwater sites had conditional inclusion as base load in Batch Zero. Childress was already operating and Sweetwater 1 was connected. For 2027, the question is whether each later Sweetwater phase can secure the approvals and equipment it needs in time for customer testing. Sweetwater 2 contributes no revenue in these cases. TCEQ’s statement on resumed reviews · ERCOT Batch Zero update · IREN’s Sweetwater announcement
How contract length changes revenue per megawatt
IREN’s newly signed three-year deals earned 11% more per IT MW than the previous quarter’s three-year deals. Five-year prices rose 12%. One five-year contract cleared near $22 million per IT MW a year. A three-to-six-month deal reached roughly $40 million. An older H100 cluster renewed at twice its previous price. Customers were paying for access to scarce capacity, even when the hardware was already a generation or two behind.
There is evidence for that reading beyond IREN. Nebius reported landmark deals at $20 million to $25 million per MW and customer advances covering 50% to 60% of associated capex in 70% of deals. CoreWeave reported three-to-six-month contracts near $40 million per MW in September. The term matters. A lender can give credit for several years of contracted payments. A short booking must be won again after a few months, and its attractive rate earns nothing while a cluster sits idle. Nebius shareholder letter · CoreWeave pricing update

Why five-year deals take 65% of new capacity in the base case
We expect 65% of newly sold base-case capacity to go to five-year buyers, 30% to three-year buyers and 5% to shorter bookings. We use $22 million per liquid-cooled IT MW on a five-year agreement, the price IREN actually disclosed. Three years earns $23.5 million. Short bookings earn $38 million after time between customers. By December, new deals across air- and liquid-cooled halls average $22.97 million per IT MW, compared with $13.40 million for the reserved book.
New-contract package | Bear | Base | Bull |
|---|---|---|---|
Five-year share | 80% | 65% | 50% |
Three-year share | 18% | 30% | 40% |
Short-duration share | 2% | 5% | 10% |
Five-year price, liquid, per IT MW | $19M | $22M | $25M |
Three-year price, liquid, per IT MW | $21M | $23.5M | $28M |
Short-duration price, per IT MW | $30M | $40M | $44M |
Blended liquid revenue per IT MW | $19.52M | $23.25M | $27.97M |
Customer prepayment, share of GPU capex | 45% | 60% | 85% |
Term GPU financing, share of GPU capex | 40% | 30% | 5% |

That price gap explains why the last round of construction is so valuable. In June, only 30 paid MW earn new-contract rates. By December, 315.8 MW do. A Microsoft hall keeps its original price throughout. The fleet earns more per MW because the mix of customers changes.
Mirantis gives IREN another way to compete for those customers. Its software manages clusters and already supports the NVIDIA agreement. If more buyers choose IREN to run their software environment as well as supply machines, those services could improve renewals or pricing. We give the 2027 forecast no separate Mirantis software premium. A contract that discloses what a buyer will pay for the added service would give us the first good basis for one. IREN’s Mirantis acquisition
IREN’s funding gap through June and its second-half capex
Management’s fiscal year ends in June. Its update identified about $15 billion left to spend between October 2026 and June 2027. Cash, committed facilities and contracted prepayments covered about $9 billion, leaving roughly $6 billion to raise. Our base puts $5 billion of payments in the December 2026 quarter and $10.21 billion in the first half of 2027. On the same dates, our $15.21 billion is close to management’s figure. IREN’s first-quarter filing

Then July arrives. We expect another $16.64 billion of capex through December, outside the period covered by that funding update. Part of what makes the second half demanding is a contract IREN has already signed. Its $6.7 billion of Dell orders call for payment within 30 days of shipment. A customer that needs a few extra weeks to test a hall can push back billing. Dell’s invoice is still due. Dell order and payment terms in IREN’s filing
How customer prepayments and debt finance construction
Consider one of management’s illustrations. One IT MW needs $40 million of GPUs and $20 million of data-center investment. A customer that prepays 90% of the GPU cost supplies $36 million up front. IREN has $24 million left to fund. Over a five-year contract the customer then uses $7.2 million a year of service credits. The advance finances the equipment, and part of each subsequent bill has already been paid.

For the base fleet we assume a more modest 60% prepayment on eligible new GPU costs. IREN collects $9.75 billion of advances over the year and draws $17.71 billion of new debt. Much of the borrowing relies on GPUs and signed customer contracts. The less certain part is $2 billion borrowed against data centers at 8% and a $3 billion corporate facility at 10.5%. Management has outlined potential financing against those assets. The facilities still need lender signatures.
Base case, 2027 | Amount |
|---|---|
Capex payments | $26.85B |
Debt and lease principal repayments | $2.78B |
Financing fees | $0.34B |
Total uses | $29.97B |
Operating cash before advances | $1.88B |
Customer advances received | $9.75B |
New debt | $17.71B |
New equity | 0 |
Reduction in cash balance | $0.63B |
Total sources | $29.97B |
By year-end the business carries $27.59 billion of debt and leases. July is the tightest month, with $1.96 billion of unrestricted cash against the $2 billion reserve we would like IREN to hold. A lender can also restrict cash at an individual project, which makes the amount available to the parent as important as the consolidated balance. A signed corporate facility with a clear draw schedule would change our confidence more than another announcement about potential megawatts.
Why 2027 revenue trails the year-end run rate
Most of the first quarter belongs to the original customer book. Revenue in our base case is $650 million. By the fourth quarter the Texas liquid-cooled halls have begun serving buyers at newer prices. Revenue reaches $2.35 billion in that quarter and EBITDA before stock compensation reaches $1.76 billion. On December 31 we can annualize the contracts actually billing that day. That gives $12.99 billion, more than twice the $5.86 billion earned over the whole year.

Base case, 2027 | Q1 | Q2 | Q3 | Q4 | Year |
|---|---|---|---|---|---|
Billing IT MW, quarter end | 347.5 | 442.5 | 490.2 | 743.3 | 743.3 |
Revenue | $0.65B | $1.24B | $1.62B | $2.35B | $5.86B |
EBITDA before stock compensation | $0.37B | $0.86B | $1.17B | $1.76B | $4.15B |
EBITDA margin | 56.6% | 69.1% | 72.0% | 74.8% | 70.8% |
Depreciation | $0.50B | $0.79B | $0.92B | $1.42B | $3.63B |
Normalized net earnings | ($0.36B) | ($0.27B) | ($0.10B) | ($0.11B) | ($0.84B) |
Exit run rate, quarter end | $4.23B | $6.17B | $7.13B | $12.99B | $12.99B |
That growth still leaves a normalized net loss of $840 million for 2027. The largest expense below EBITDA is $3.63 billion of depreciation on the installed assets. Financing costs charged to earnings add about $1.03 billion and stock compensation another $400 million. Shareholders who avoid issuing stock to pay suppliers still pay for the debt that took its place. Even without selling common stock for cash, settling employee compensation in shares takes ordinary shares from about 426 million to 460 million.
How much capacity starts billing in the bear, base and bull cases
The bear case takes a month or two of delays, little more. IREN pays for the GPUs it has already ordered and defers 207.5 IT MW of additional orders. It still spends $17.25 billion, because holding back a future order does little for a supplier invoice due this month. Only 526.7 MW are billing at year-end. In our base, all 855 MW are equipped and 743.3 MW have been accepted. In the bull case, customers take all 861 MW, pay richer rates and advance 85% of eligible GPU costs. That last assumption is the biggest commercial stretch. One 90% deal shows what a buyer will do for a scarce slot. It takes many such buyers to fund a fleet.

How a $6 billion equity raise would dilute shareholders
Financing can change the outcome even if every site keeps exactly the same schedule. If the corporate facility fails to close and data-center borrowing stalls, our funding-stress case runs the bear fleet but raises about $6 billion of equity at the $11.82 reference price to protect cash. IREN ends up with roughly 970 million ordinary shares. It can deliver the same service to the same customers and leave each holder with about half the ownership they would otherwise have had.
Case outputs, 2027 | Bear | Base | Bull |
|---|---|---|---|
Revenue | $4.91B | $5.86B | $7.43B |
EBITDA before stock compensation | $3.28B | $4.15B | $5.57B |
Normalized net earnings | ($1.43B) | ($0.84B) | $0.23B |
Exit annualized revenue, December | $7.58B | $12.99B | $17.77B |
Billing IT MW, December | 527 | 743 | 861 |
Capex | $17.25B | $26.85B | $27.21B |
Customer advances received | $3.62B | $9.75B | $13.27B |
New debt | $14.05B | $17.71B | $13.62B |
Debt and leases, December | $23.96B | $27.59B | $23.62B |
Lowest unrestricted cash | $0.43B | $1.96B | $1.32B |
Ordinary shares, December | 460M | 460M | 460M |
Those 460 million or 970 million shares each represent a claim on the cash the fleet can earn. Even in the base case, lenders have a claim on that cash, and customers who paid for GPUs in advance can settle part of their future bills with credits. How much of the fleet’s value is left for each share once those claims are paid?
Northwise Premium
Choose how to continue with Northwise
Join Northwise Premium
Unlock the rest of this report, its complete valuation, the downloadable model, portfolios, and action framework.
Join Northwise PremiumCreate a Free Account
Continue across Free Northwise research, follow companies, save reports, and receive updates.
Create a Free AccountReader discussion
Discuss the research
Premium access is required to join this report's discussion.
Join Northwise Premium




No comments yet. Start a thoughtful discussion.