IREN Nolan County and Scurry County Data Center Plans
Texas filings point to two potential IREN campuses in Nolan and Scurry counties.
In this article
A dispute over three miles of power line has brought two potential new IREN data center sites in West Texas into view. Testifying about farmland southeast of Roscoe, IREN’s development director described an AI campus planned for Nolan County. In the same filing, he identified a second planned facility in neighboring Scurry County. Jason Date’s sworn testimony, PDF pages 8–10
For investors following IREN’s Texas buildout, this is a glimpse of where the company could go next. IREN has already delivered its first Horizon facility to Microsoft at Childress. At Sweetwater, two named sites account for its entire announced 2 GW hub. Nolan and Scurry put two more places on the map where IREN wants to build. The company has yet to disclose a power commitment or an opening date for either. IREN’s November earnings release · IREN’s Sweetwater announcement
Nolan is the site we can trace. IREN bought its first land there in 2024 and went on to assemble roughly 827 acres through deeds and purchase options. When Oncor proposed running a line diagonally across one of those fields, IREN had to explain why the layout mattered to the economics of the whole campus.
Scurry is harder to pin down. The same IREN subsidiary owns a 591-acre holding just northwest of Roscoe, near the Fisher County line. The witness confirmed a facility plan for Scurry County. Whether IREN intends to put the buildings on those particular acres is still open. Sworn land table and facility description · Scurry County ownership record
Where the two sites fit on IREN’s Texas map

Childress sits farther north. The inset shows how close the two potential sites are to the Sweetwater hub. The Nolan circle marks the area named in testimony. The Scurry diamond marks IREN-owned land whose use as the facility site remains unconfirmed. Locations are approximate. Company hub map, slide 6 · Texas filing for Childress.
The short distance to Sweetwater raises an obvious question. Could the Roscoe land already be part of the two-site hub? IREN’s own investor map places Sweetwater 1 at 1,400 MW and Sweetwater 2 at 600 MW, about 28 miles apart. Texas environmental records put the first development on FM 611 in Fisher County and explicitly identify Sweetwater 2 on FM 540 near Hamlin, also in Fisher County. Texas environmental registry, three Fisher County records
Jason Date, associate director of development for IREN subsidiary IE US Development Holdings 1 Inc., placed the Nolan land south of Interstate 20 on both sides of County Road 152 near FM 608. It is a different set of fields. IREN’s September statement on ERCOT’s conditional Batch Zero treatment applied to the two named Sweetwater sites. The company has disclosed no arrangement bringing Roscoe into that hub or giving it a share of those megawatts. Roscoe location in testimony · IREN’s Batch Zero announcement
How IREN assembled the land
The first purchase was modest. A July 29, 2024 general warranty deed covered 40.004 acres. An April 10, 2026 special warranty deed added 196.78 acres across four more routing tracts. Date identified both instruments in his sworn testimony, along with the six tracts the company held under purchase options. Together the options cover about 590 acres. They account for most of the land available to the proposed campus, leaving IREN with a meaningful decision about how much to acquire as development progresses. Sworn land table and deed references, PDF page 5
There are two legitimate figures for the owned land. The Nolan County certified appraisal roll lists five assessments under Holdings 1, all in Section 58 of Texas & Pacific Railroad Block 23, totaling 240.004 acres. The surveyed descriptions in Date’s testimony total 236.784 acres. The first purchase matches to the thousandth of an acre in both records. The other four assessments total 200 acres against 196.78 in the April deed description. Using the witness’s figures consistently puts the owned-and-optioned assembly at roughly 827 acres. IREN has not specified how much of it would carry buildings. Nolan County’s certified appraisal roll, CSV

Why a diagonal line could change the economics
Oncor wants to build a roughly three-mile, 138 kV transmission line between its Plowboy substation and its planned Oak Spring switch. It proposed twenty possible routes. On August 28, IREN’s subsidiary intervened as an affected landholder. Its concern was where the line would run across the fields. Oncor project description · Motion to intervene
Find tract 1045 on the left side of Oncor’s filed map. Link J crosses it diagonally. Date testified that the land taken up by the line and its required setback could render that tract unusable for the planned campus. Its size and position meant that losing its use could make the other tracts uneconomic to develop together. A line along the tract’s edge would leave IREN a more useful block of land. Date on tract 1045, PDF pages 8–10

Blue marks owned land and pale blue marks land under option. The dotted alignments are proposals in the routing case. Open Oncor’s full-resolution map and original legend, PDF page 4.
IREN preferred Route 98, which would run around the properties. It also offered a compromise. The owners of optioned tracts 1045 and 1049 signed consents for modified alignments. In its October 23 reply, Oncor told the regulator it did not oppose modifications for which IREN had secured the necessary consent. That gives the commission alternatives that could preserve the layout. The public docket contained no final route order as of November 22. Signed consents · Oncor’s reply brief · Commission docket 60008
What power has IREN actually secured here?
No site-specific MW, utility service agreement or first-power date has been publicly verified for Nolan County. The 138 kV figure measures the proposed line’s voltage. Oncor applied to strengthen its regional transmission network and defended the need for the line using load growth across five counties. IREN participated because the route could affect its land. Its participation gives us unusually good evidence about the campus plan, but no allocation of electricity to it. Oncor’s regional load case, PDF pages 13–18
Oncor anticipates a routing decision in January 2027 and plans to complete its line in 2028. The first date could tell investors whether IREN retains the layout it wants. The second belongs to the utility’s construction schedule. A service agreement or an IREN disclosure naming the campus and its contracted load would establish a power position. Construction, energization and customer delivery would each require their own evidence. Oncor’s project schedule

Scurry County has a separate lead
Scurry gets a single line in Date’s testimony. He identifies “another planned facility in Scurry County, Texas” and then returns to Roscoe. A county land record from six months earlier gives that reference a place to start. The Scurry County Appraisal District lists the same IREN subsidiary as the 100% owner of parcel 21474, assessed at 591 acres in Block Y, Section 22. The appraisal card gives a March 13, 2026 deed date and instrument number 20261218. A former listing places the property along U.S. 84 near the Nolan and Fisher county lines. Scurry disclosure, PDF page 9 · County appraisal and deed history · Former farm listing
The county record makes it a credible location to investigate. A detail in the map shows why it would be premature to draw a campus around it. The listing describes farmland on both sides of the highway. The county GIS query for parcel 21474 returns a single polygon of approximately 192 acres, while the same record’s acreage field says 591. The aerial below outlines only the geometry the county returned. No site plan or permit reviewed identifies which land IREN intends to develop for computing. Scurry appraisal district GIS

Gold outlines one mapped portion of the assessed holding. The county figures describe land ownership. IREN has identified its planned facility only at county level. Imagery from the USGS National Map.
Other Scurry projects already have megawatt figures attached to them. The Cavender Road data center abatement covers different parcels under different development entities. Energy Vault separately discloses a Crusoe deployment in Snyder. Neither supplies a power or construction figure for IREN’s Scurry lead. County’s executed Cavender Road agreement, Exhibit A · Energy Vault’s SEC filing
What would turn these plans into campuses?
IREN’s November earnings release put its secured power above 5 GW and its development pipeline above 35 GW. It assigned neither figure to Nolan or Scurry. The next decision in Nolan is whether IREN can keep enough contiguous land to lay out the campus it described. For Scurry, the first breakthrough would be a permit or site plan that finally puts the proposed facility on a specific tract.
Once the route is settled, an option exercise at Roscoe would show IREN committing more capital to the land. A signed utility agreement in either county would tell shareholders how much power IREN can secure there and when service could begin. Those are the steps that could turn two promising locations into a larger Texas buildout. IREN’s November 5 earnings release and pipeline definitions
Follow the two locations in the Nolan County tracker entry and the Scurry County tracker entry. For the rest of the portfolio, see the IREN infrastructure hub and the IREN forecasting workspace.