NBIS Alabama Data Center
A complete Nebius Birmingham site report covering Oxmoor history, capacity, delivery targets, power, cooling, local permits and moratorium litigation.
In this article
The old Regions Bank property on Milan Parkway is becoming one of Nebius's most consequential US construction projects. On roughly 75 acres in Birmingham's Oxmoor Valley, the company is replacing a back-office site with an AI campus, building the electrical infrastructure to support it and defending its approvals in court at the same time.
Birmingham adds an owned southeastern US campus to a network expanding through both direct development and colocation. Ownership gives Nebius more control over facility design and expansion. It also puts the construction bill, the utility work and the consequences of a delayed opening squarely on the company. The investment case depends on turning that control into computing capacity customers can use.
Where Birmingham stands today
Birmingham is under construction, with issued building and electrical permits and a live legal challenge to its approvals. The strongest evidence of progress is the sequence in the city's records: foundations, superstructure, the Phase 2 shell, a substation and high-voltage electrical work, followed by fire-system applications in October and November. This is a project moving through construction and trade permitting.
The remaining delivery work is substantial. The Phase 2 approval covers a shell and reserves the complete interior buildout for a later submission. The latest sprinkler and fire-alarm applications were still marked Submitted on November 8. Nebius then has to commission the electrical and cooling systems, complete the computing installation and bring customers into service. Active IT capacity has not been publicly disclosed.
The legal risk is specific. Birmingham treated Nebius as exempt from its March moratorium and continued issuing permits. Residents are challenging that treatment and the city's decision to allow the electrical facilities without special exceptions. Related court proceedings continue on March 8, 2027, with a permanent construction injunction among the remedies sought. For the investment case, that creates exposure around both the opening schedule and later expansion.
Our assessment: Birmingham has a much stronger starting position than an unpermitted site, but it still carries meaningful construction and legal risk before it can support the 2027 operating plan. The physical development is advancing. The amount of capacity delivered in each phase, and the outcome of the approval challenge, will determine its contribution to Nebius.
The underlying evidence is in Birmingham's permit portal, the city's account of the moratorium exemption, the September court order and October reporting on the injunction proceedings.
Birmingham at a glance
Item | Current picture |
|---|---|
Location | 201 Milan Parkway, off Lakeshore Parkway in Birmingham's Oxmoor Valley, Jefferson County, Alabama |
Property | Approximately 75 acres acquired in September 2025; formerly a Regions Bank back-office property |
Development | Two-building campus designed, owned and operated by Nebius; Hoar Construction is the general contractor |
Reported scale | 300 MW of project scale in local reporting. Nebius has not published a phase-by-phase IT-capacity allocation |
Active capacity | Commissioned Nebius IT MW has not been publicly disclosed as of November 8, 2026 |
Company targets | Q4 2026 initial commissioning and energization; operations in 2027; construction continuing through 2028 |
Power infrastructure | Issued permits for a 230 kV to 34.5 kV substation and high-voltage electrical work |
Principal exposure | Remaining fitout and commissioning, plus litigation challenging the existing approvals |
The Nebius project page, project overview and May shareholder letter, page 6 set out the property and development targets. Local coverage describes the project as 300 MW.
Follow the Birmingham tracker entry, compare locations in the Nebius site hub, or explore the yearly model reports.
The campus and the power parcel across the road
Milan Parkway meets Lakeshore Parkway at the eastern edge of the development. The campus application covers the parcel group south of Milan. A separate electrical-infrastructure parcel sits across the road at 260 Milan Parkway. That geography helps explain why the project generated two electrical zoning cases and why both matter to the same campus.
The city's March 26 zoning agenda, page 1 identifies Alabama ADC Holdings as the owner in both applications. Case ZBA2026-00007 concerns the substation supporting the data center at 201 Milan. Case ZBA2026-00006 concerns Lot 6 at 260 Milan, which the city attorney subsequently described as the related switching-station request.

The map combines those application references with the city's Accela parcel and road GIS. Three of the four campus parcel identifiers match directly. The agenda's remaining identifier is malformed; the hatched parcel matches the city's 201 Milan address and Lot 10 record. The map shows application land and the surrounding streets, rather than an approved equipment or building layout.
Nebius acquired the former banking property in September 2025. The redevelopment involves demolition and new construction. The master permit, BLD2026-00036, combines demolition of the Regions building with new data-warehouse construction. The foundation record authorizes the structural work for that stage.
The old property gives Nebius an established commercial location, but the AI campus requires a new building and utility program. Its setting also brings established neighbors into the development process. Residents and the Greater Birmingham Humane Society have challenged the project's compatibility with surrounding uses, making siting, sound and the treatment of the electrical facilities central to the dispute.
Capacity and the route into service
The reported 300 MW describes the scale of the development. It is not a disclosed amount of active IT capacity. Power at the utility connection, total facility demand and power available to computing equipment are different quantities because cooling and electrical systems consume power too. Nebius has yet to publish Birmingham's phase-by-phase IT MW and customer-acceptance schedule.
The company has given three milestones. Its community page targets initial commissioning and energization in Q4 2026. The May 13 shareholder letter places Alabama and Missouri among owned sites expected to become operational in 2027. Construction for Birmingham's full buildout continues through 2028 on the community schedule.

An initial energization can precede customer service, while construction continues on later phases. Those stages explain how the dates can fit together. The public schedule does not promise that the entire campus will be available in 2027.
For shareholders, the ramp matters as much as the opening date. A phase accepted in November contributes far less revenue that year than the same capacity available in January. Birmingham can finish a year with a substantial operating footprint while contributing only a fraction of a full year's earnings from that footprint. The yearly models need the delivery dates and accepted IT capacity behind the campus headline.
GPU installation, networking and customer acceptance remain part of that ramp. The public material does not establish Birmingham's installed GPU mix or utilization. Historical energy and PUE illustrations are retained at the end of this report with their original assumptions.
What the permits show
The city portal's 2026 records for 201 Milan Parkway trace a staged build. Foundations and the superstructure came first, followed by the Phase 2 shell and substation. More recent records cover high-voltage work, sprinklers and fire alarms. The table reflects statuses displayed on November 8; dates are record dates unless issuance is specified.
Record | Date and status | Scope |
|---|---|---|
BLD2026-00195 | January 29; Issued | Foundation only, with structural pages approved for construction |
BLD2026-00640 | March 30; Issued | Building superstructure |
BLD2026-00724 | April 10; Issued April 27 | Phase 2, two-story steel building shell. Complete interior buildout reserved for a future submission |
BLD2026-00780 | April 16; Issued | 230 kV to 34.5 kV substation for DCFL BHM01 |
BLD2026-00724.REV1 | June 11; Closed - Withdrawn | Proposed added height and a basement for mechanical equipment. Withdrawn June 26 |
ELE2026-01902 | September 8; Issued | High-voltage electrical work associated with the substation |
FPT2026-00380 | October 22; Submitted | Seven new fire-sprinkler systems |
FPT2026-00388 and LVE2026-01002 | November 2; Submitted and Issued, respectively | Fire alarm/VESDA installation and a separate fire-alarm cabling permit |
The source entries include the Phase 2 shell, substation building permit, high-voltage electrical record, sprinkler application and fire-alarm application.
The progress is the breadth of authorized work and the continued arrival of trade applications. The unfinished portion is just as concrete: the shell permit defers interior buildout, and the latest fire-system applications remain in review. Issuance authorizes construction; completion and acceptance come later. The withdrawn June revision also means its proposed basement and added height cannot be treated as the approved final design.
The fire applications show another stage of the work moving through the city. Their Submitted status alone does not establish a delay. The delivery question is whether those approvals, installation and inspections finish in time for the phase Nebius intends to open.
Power, cooling and the neighborhood
Nebius says it will fund the new Alabama Power switching and substation infrastructure. The city's issued records identify the substation as a 230 kV to 34.5 kV installation. This is the electrical connection and voltage transformation needed to feed the campus. The utility supply, switching equipment, transformers, internal distribution and protection systems must work together before the computing load can be brought online.
Construction also has environmental obligations. The EPA record for ALR10C7R7 identifies Hoar Construction's coverage under the construction stormwater general permit, originally issued February 18, 2026, with an effective record dated June 26.
For cooling, Nebius's October community answers describe a sealed loop that recirculates water and rejects heat mechanically to the air. The company projects annual water use below one million gallons, compared with more than three million gallons at the former Regions facility.
That choice reduces ongoing water demand, while putting greater emphasis on the fans and heat-rejection equipment outside the halls. Nebius's sound-control design includes walls between eight and 22 feet, low-noise fans, acoustic canopies over dry coolers and four enclosed backup generators. It plans roughly 1.5 hours of monthly maintenance operation for the generators and cites an AEI engineering sound study supporting its noise projections.
For nearby residents, those details determine how the completed campus will sound and operate. For Nebius, they affect equipment placement, available land, construction cost and its ability to satisfy local conditions. Cooling and sound control are part of delivering the site, alongside the electrical buildout.
How the city allowed construction, and why it is being challenged
Birmingham initially proposed a 270-day pause on new data-center applications in December 2025. The measure adopted on March 3, 2026 was a 180-day moratorium. The city's April District 8 newsletter, page 3, says Nebius and the DC BLOX expansion were exempt because their permitting processes had already begun. That treatment allowed Nebius to continue through the city's approval process while new applicants faced a pause.
The electrical facilities created a separate dispute. The March 26 zoning-board requests did not secure approval. The substation motion received three votes in favor, one opposed and one abstention, falling short of the four affirmative votes required. The switching-station request was denied.
The April 9 city-attorney memorandum, reproduced in Exhibit A on PDF pages 46-48, explains what happened next. The attorney concluded that the proposed facilities served a single user and therefore fell outside the ordinance's definition requiring a special exception for utility substations serving individual neighborhoods. On that interpretation, neither request needed zoning-board approval. The memo also said the determination could be appealed.
That is the central zoning issue. The city proceeded on its interpretation; opponents are asking the court to reject it. The residents' amended complaint also challenges Phase 2's eligibility for the moratorium exemption. Its April 10 application record and April 27 issuance both follow the March 3 adoption, which makes the treatment of later phases important to the case.
The September 17 order consolidated three related cases and retained the existing schedule, including limited additional evidence from the humane society on March 8, 2027. WBRC's October account identifies a permanent injunction against construction as the issue before the court. The consolidation order did not stop construction or decide the validity of the permits.
An October 28 ruling narrowed the case. According to WBHM's October 29 report, the judge dismissed Lakeshore Data Center, LLC as a defendant and three of eight counts against the remaining defendants. Two counts were dismissed permanently; the claim over potential future operating nuisances was dismissed without prejudice, allowing it to be brought again. The main permit challenges remain for the March trial. The ruling reduces the claims Nebius faces while leaving the central construction dispute unresolved.

Birmingham also adopted new data-center zoning conditions on June 9. The rules address siting, water, noise, backup generation, utility capacity and phased development, including further compliance review when facility scale increases. The practical risk for Nebius is therefore concentrated in the challenge to its existing approvals and the treatment of later expansion or design changes under the new rules.
The moratorium exemption was a significant advantage. It kept the project moving. It does not settle the court challenge or guarantee approval of every future phase.
The financial stakes
Nebius's project overview projects about $85.77 million in annual taxes over 30 years across Birmingham, Jefferson County and Alabama. The size of that expected contribution helps explain the city's support for the development. Separate litigation reported in September concerns the property transaction and tax abatement, adding an economic dispute alongside the construction case.
At the state level, the Public Service Commission's October 6 minutes, pages 14-18 establish a process for large-load data-center electricity contracts. Public petitions are to identify the customer, location and maximum contracted capacity. The process includes deemed approval if the commission does not vote within 90 days. A Birmingham-specific filing could provide a firmer view of its contracted power; the statewide rule alone supplies no new site MW.
For Nebius, the financial benefit of ownership depends on delivering enough usable capacity to justify the capital committed. A delay can leave cash tied up in land, buildings, electrical systems and equipment before customer revenue starts. Conversely, a successfully commissioned campus gives the company a durable platform it can develop around its computing architecture and future demand.
Why Birmingham matters to the wider Nebius buildout
Birmingham adds both geographic and operating diversity. Nebius is building owned campuses while also using major hosts such as Vineland and separate facility providers at sites such as CLT1. These projects spread development across different local authorities, utilities and construction arrangements.
That mix gives Nebius several routes to adding capacity. A setback in Alabama does not automatically stop a site in another state. It can still matter materially to the company if the delayed capacity was needed for a particular deployment, or if equipment and capital have already been committed to it. Hardware procurement and financing can also connect projects that look independent on a map.
Birmingham's next milestones are practical ones: an energized phase with a stated power scope, completed fitout and fire-system approvals, accepted computing capacity and a customer-service timetable. The March 2027 proceedings may also change what Nebius can build and when. Together, those developments will show how much of this owned-campus investment reaches the operating business in 2027 and how much remains for later years.
The Birmingham tracker follows the site, the Nebius hub puts it alongside the rest of the network, and the year-specific model reports show how delivery assumptions affect the financial outlook. Each dated model keeps its original assumptions, allowing members to compare the buildout as it unfolds with what Northwise expected at the time.
Historical calculations retained from the original study
The following limited examples are preserved from the original publication. Their assumptions and outputs have not been revised. They are not current operating measurements, a new Northwise forecast or a statement of current contracted prices. The factual discussion above uses the latest reviewed evidence.
The retained examples use both 300 MW facility-load and 300 MW IT-load assumptions. They are separate illustrations and must not be combined or treated as verified operating measurements.
Utility Metric | Estimate (300MW Facility) |
|---|---|
Continuous Power Draw | 300MW |
Annual Electricity Consumption | ~2.6 million MWh |
Equivalent Residential Load | ~250,000–300,000 homes |
Efficiency Variable | Impact at 300MW Scale |
|---|---|
1% Power Efficiency Gain | ~26,000 MWh annually |
5% Efficiency Gain | ~130,000 MWh annually |
20% TCO Improvement | Compounds across GPU lifecycle |
PUE Scenario | Effective Total Load at 300MW IT |
|---|---|
1.60 | 480MW total facility load |
1.30 | 390MW total facility load |
1.20 | 360MW total facility load |
Reader discussion
Discuss the research
Create a Free account to join the discussion with a display name.
Create a Free Account




No comments yet. Start a thoughtful discussion.