Northwise

CIFR Stock Data Center Analysis

Research Note · FreePublished · Updated

A guide to Cipher Digital’s data centers, including Black Pearl’s first rent, the amended Barber Lake lease and Horizon in Texas.

In this article

Cipher Digital's data center portfolio now spans operating Bitcoin infrastructure, three contracted HPC campuses and a much larger development pipeline. The important change is that the first contracted HPC capacity has started earning rent. The important remaining distinction is that most of the advertised megawatts are still future projects.

The directory brings together Cipher’s August site inventory and the changes the company disclosed on November 2, including its acquisition of Horizon. The Cipher Data Center Tracker follows these projects alongside other operators.

Cipher’s named sites

The table starts with Cipher’s August portfolio presentation and incorporates its November business update. MW figures describe gross electrical capacity. Future dates are management targets.

Site

Gross capacity

Reported stage or target

Black Pearl

300 MW

First HPC capacity delivered; later phases under construction

Barber Lake

300 MW

Phased delivery under amended 20-year lease

Stingray

100 MW

Contracted; delivery targeted H1 2027

Odessa

207 MW

Bitcoin mining; HPC discussions

Reveille

70 MW

Substation development; Q3 2027 target

Ulysses, Ohio

200 MW

Substation development; Q4 2027 target

Colchis

1,000 MW

Conditional base-load classification in ERCOT’s Batch Zero process

Mikeska

500 MW

Grid development; 2028 target

McLennan

500 MW

Grid development; 2028 target

Milsing

500 MW

Grid development; 2030+ target

Apollo

Up to 900 MW

Site option; 2030+ target

Horizon, Texas

70 MW

Acquired in Q3, with energization targeted for 2029

The same presentation identifies potential additions at Barber Lake and Stingray. These are expansions of existing locations, so counting them as separate campuses would overstate the site count. The inventory deliberately keeps one row per named site.

What has changed at the contracted sites

Black Pearl. Cipher recognized its first HPC lease revenue here in the third quarter. Equipment installation continued in later halls as the first delivered capacity began earning rent.

Cifr stock black pearl site northwise

Read the Black Pearl site study

Barber Lake. The amended lease runs for 20 years, with deliveries phased around the tenant’s compute rollout. Cipher said in November that construction was tracking the revised milestones.

CIFR Barber Lake Site Northwise

Read the Barber Lake site study · Cipher’s November update

Stingray is now an identified, financed project. The same update reported completion of its $810 million financing, intended to fund development through substantial completion. Treating the site as a guess about an unnamed third lease is obsolete.

The three projects still need to be followed separately. A tenant's early access, partial occupancy, rack installation and rent commencement can occur at different milestones. Combining them into one company-wide label such as "operational" hides the most useful information.

September's generation development

On September 3, Cipher announced lateral gas-pipeline development intended to support up to 2.5 GW of on-site electricity generation across multiple locations, with new power targeted before the end of 2027. Power providers would develop and operate the generation infrastructure.

That is a development programme, not an announcement that 2.5 GW is already energized. It also cannot simply be added to every grid-connected site. An allocation needs evidence identifying the location, generation capacity and overlap with existing plans.

In its November update Cipher put its development pipeline at approximately 5.9 GW. The total spans projects at different stages. At Colchis, for example, 1 GW received a conditional grid classification. The company still has to develop the site before it can earn rent.

Former sites and ownership

Cipher's June-quarter filing records the February 19 sale of its 49% interests in Alborz, Bear and Chief Mountain. Those names belong in the company's history, not in today's owned development inventory.

Ownership matters throughout the portfolio. A site option is different from a completed purchase, and control of a development is different from ownership of the tenant's GPUs. Cipher's operating model centres on delivering the physical campus and its contracted services.

How to read the next update

The useful sequence is site control, usable power, construction, tenant acceptance and revenue. A lease reduces demand uncertainty, but leaves delivery and financing obligations. A financing announcement improves the funding position, but does not make the customer ready to pay.

The site studies above explain those dependencies at Black Pearl and Barber Lake. For the broader business model and research archive, see Cipher Digital coverage.

Northwise Research

Get Northwise Research in Your Inbox

New research, model releases, portfolio updates, and major Northwise developments delivered directly to your inbox.

Reader discussion

Discuss the research

0 published

Create a Free account to join the discussion with a display name.

Create a Free Account

No comments yet. Start a thoughtful discussion.