Where CoreWeave operates and where it plans to expand, from its first UK deployments to contracted capacity in India and Indonesia.

In this article

CoreWeave reported over 1.7 GW of active power and over 4.6 GW under contract in its November 10 update. The first figure describes power brought into the fleet. The second includes capacity reserved for future delivery. A customer can run a job only after the necessary equipment and cloud service are available. CoreWeave’s third-quarter results

This directory covers the named projects, cloud service locations and hiring leads in the CoreWeave tracker. Some hosts disclose a leased building. Others report figures for a whole portfolio. The unit of disclosure matters when estimating how much capacity is ready for customers.

United States and Canada

Kenilworth, New Jersey

CoreWeave is both developer and operator of NEST 11, a former pharmaceutical research building being adapted for AI computing. The company lists a planned 40 MW load. Readers following this redevelopment should look for a commissioning or customer-service announcement before treating that figure as active. CoreWeave’s Kenilworth project page

Lancaster, Pennsylvania

CoreWeave announced an initial 100 MW project in Lancaster, with room for a potential expansion to 300 MW. Its commitment was to equip the data center. The possible expansion includes the initial phase, so adding the two figures would count it twice. CoreWeave’s Pennsylvania announcement

Host portfolios and other North American locations

At September 30, host Core Scientific reported that 485 MW of the 590 MW leased to CoreWeave was billable. The remaining 105 MW was still being built or commissioned. This portfolio disclosure measures what the host can bill under its leases. CoreWeave reports active power across its entire fleet using a different measure. Core Scientific’s September-quarter filing

Core Scientific locations. The tracker identifies Austin and Denton in Texas, Dalton 1 and Dalton 4 in Georgia, Marble in North Carolina and Muskogee in Oklahoma. The host reports billable capacity across the portfolio. Its quarterly figure cannot tell us how much of any one location CoreWeave was using.

Other U.S. projects. In the East, entries include DataBank Orangeburg in New York, LGA1 in Weehawken, New Jersey, and the Chirisa and PowerHouse programme in Richmond, Virginia. In the Midwest and Mountain West, the map includes Chirisa’s Volo Technology Park in Illinois, Polaris Forge 1 in Ellendale, North Dakota, and the first building of Related Digital’s Cheyenne project in Wyoming.

Plano and other host facilities. The tracker also follows Galaxy’s Helios campus and two Plano records. One identifies Flexential Dallas-Plano. The other comes from CoreWeave’s 2023 Plano deployment disclosure. The two disclosures do not establish how many distinct buildings CoreWeave occupied in Plano. Flexential’s Douglasville, Georgia, and Hillsboro, Oregon, are separate entries. Las Vegas appears as a historical campus.

Canada. The tracker identifies eStruxture CAL-3 in Alberta. Cambridge, Ontario, appears separately because of deployment hiring. That evidence identifies a market where CoreWeave was recruiting. It leaves the building, tenant agreement and service date open.

U.S. hiring leads. The same distinction applies to Caledonia in Michigan, Elk Grove in Illinois, Lynnwood and Quincy in Washington, Miami in Florida, Sandusky in Ohio and Sparks in Nevada. We keep these leads separate from the named projects above.

United Kingdom and continental Europe

Crawley and London Docklands

CoreWeave dates the Crawley opening with Digital Realty to October 2024 and the London Docklands opening with Global Switch to December 2024. These are two separately identified deployments with operating dates. A UK investment commitment on its own would tell a reader much less about service availability. CoreWeave’s UK opening announcement

Copenhagen, Denmark

On October 27, 2026, CoreWeave said most of its planned 22.5 MW of IT capacity at atNorth’s Copenhagen facility was online. It did not quantify the exact amount already in service. The announcement also described an international network expansion. A network presence in a country serves a different purpose from a data hall running local workloads. CoreWeave’s Denmark update

CoreWeave’s service-location listing names Skovlunde in the Copenhagen area. A service listing identifies where customers can request compute. It does not by itself establish a second Danish campus.

Barcelona, Falun and the wider European fleet

CoreWeave’s IPO filing identified Barcelona in Spain and Falun in Sweden alongside London in its 2024 European footprint. It disclosed active power for the three locations together. Dividing that figure equally among the cities would give each one an unsupported capacity estimate. Its later annual filing also lists Norway among the countries where it leases data center space. CoreWeave’s IPO filing

CoreWeave’s 2025 annual filing

Norway and Sweden. The tracker identifies Bulk N01 in Vennesla and Conapto Stockholm 4 South. A separate announcement refers to a second Conapto campus in Stockholm without naming the facility. Falun is the EcoDataCenter location. Barcelona is recorded at the service-location level in Spain.

India and Indonesia

Navi Mumbai, India

CoreWeave plans to lease 240 MW across three buildings with AdaniConneX. Its October announcement targeted mid-2028 for the first phase. An option for a further 240 MW would expand the original commitment if exercised. CoreWeave’s India announcement

The tracker records the AdaniConneX project under Taloja in the Navi Mumbai market. The three planned buildings belong to that project.

Indonesia

CoreWeave announced 360 MW of contracted IT power across three planned facilities and targeted 2028 for service. It said it would own and operate the computing equipment. The announcement provides a combined figure, leaving each facility’s individual allocation open. CoreWeave’s Indonesia announcement

What to watch at the next update

For an announced campus, look for the first phase that a customer can use. For leased capacity, compare the host’s delivered or billable amount with its signed lease. For an operating campus, the question shifts to how much of the available compute customers actually use. These milestones connect the site directory to the economics of the cloud business.

CoreWeave company research · CoreWeave 2030 valuation research (Premium)

Reader discussion

Discuss the research

0 published

Create a Free account to join the discussion with a display name.

Create a Free Account

No comments yet. Start a thoughtful discussion.